Advertisements   Division Home   Bid Results   Bid Tabs   Ad Report   VDOT Forms
Project Info
Order Number UPC State Project Number Last Date to Post Questions
261 110485 (NFO)PM2Q-962-F17,P401 5/19/2017
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Milling Type: Proposal
Question Date: 5/3/2017 2:51:39 PM
Can the ramps be milled in advance of paving? If so, what length of time is allowed between milling and paving?  
Answer   Date:
 
 
Subject: Ramp Closure Type: Proposal
Question Date: 5/3/2017 2:46:17 PM
Can the ramps be closed for the duration of the allowable work hours shown?  
Answer   Date: 5/3/2017 3:42:49 PM
Only the ramps that are listed on the limitation of operation. Please see “Section 108.02 limitation of operation."  
 
Subject: Time Limit Type: Proposal
Question Date: 5/3/2017 2:24:23 PM
Since this project involves night work and mix types that have a 50 degree spec, would the department consider extending the completion date until 6/29/2018?  
Answer   1 previous answer(s) Date: 5/10/2017 9:46:23 AM
The Department has reconsidered and will revise the completion date to June 30, 2018.  
 
Subject: View Proposal Type: Proposal
Question Date: 5/2/2017 8:37:00 AM
When will this proposal be available on the Falcon website?  
Answer   Date: 5/2/2017 2:09:03 PM
It is now available.  
 

Displaying questions 1 - 4 (of 4)
Page: 1 First Previous Next Last