Subject: Milling Type: Proposal
Question Date: 5/3/2017 3:19:43 PM
Can the ramps be milled in advance of paving? If so, what length of time is allowed between milling and paving?  
Answer   Date: 5/9/2017 4:02:38 PM
No, only the amount of pavement that can be paved back within 24 hours of completion of planning can be milled. See section c515c01-1116) DISINCENTIVE FOR PLANING IN MULTIPLE LANES The Special Provision for COLD PLANING (MILLING) ASPHALT CONCRETE OPERATIONS “S515B03”  
 
Subject: Ramp Closure Type: Proposal
Question Date: 5/3/2017 3:17:11 PM
Can the ramps be closed for the duration of the allowable work hours shown?  
Answer   Date: 5/3/2017 3:45:38 PM
Only the ramps that are listed on the limitation of operation. Please see “Section 108.02 limitation of operation”  
 
Subject: Time Limit Type: Proposal
Question Date: 5/3/2017 2:21:24 PM
Since this project involves night work and mix types that have a 50 degree spec, would the department consider extending the completion date until 6/29/2018?  
Answer   1 previous answer(s) Date: 5/10/2017 9:46:05 AM
The Department has reconsidered and will revise the completion date to June 30, 2018.  
 