Subject: Description of Work Type: Proposal
Question Date: 2/1/2017 3:01:46 PM
On page 107 of the proposal, Route 220, MP 12.38 to MP15.535, the SM-9.5D depth is shown as 2" and the corresponding milling is show as 2" but the lbs/sy shows 183 and the tonnage for some of the items is calculated at 183, which depth is correct?  