Question
|
|
Date:
|
11/22/2016 5:06:54 PM
|
Bid Item 2630 Luminaire 150 Watt H.P.S. has a quantity of 14ea. However, in reviewing the plans these are the same luminaires that are shown on the for the under-bridge lighting system, which are lump sum pay items.
Will the luminaires be paid separately from the under-bridge lighting system?
|
Answer
|
Date:
|
11/28/2016 2:42:18 PM
|
Please refer to Addendum 2. The measurement for Pay Items 3370, 3380, and 3390 (the lump sum Under-Bridge Lighting Systems for B-627, B-628 and B-629) are best described in the Payment note on the top right of Sheet 43 of 60 for B-628 and which applies to all three bridges. That note states that the lump sum items include under-bridge lighting components within the limits of each bridge and that this lump sum does not include the costs for luminaires or conductors which are paid separately.
|
|
|
Question
|
|
Date:
|
11/22/2016 3:26:49 PM
|
The following questions have been posted some time ago and have not been and the issue not reconciled.
Please advise when the duplicate bid items as listed below will be reconciled in the Expedite file or how the Contractor is to deal with these duplicate items
Q: Can the Department please clarify the difference between pay items 1105 & 1106 and 2333 & 2337. They appear to be the same. (11/5/2016 9:04:34 PM)
A: Pay items 1105 and 1106 should have been replaced by 2333 and 2337 respectively in Addendum #2. Delete pay items 1105 and 1106. (11/10/2016 9:54:17 AM)
Q: The new Expedite file that was just posted on Bid Express still contains both sets of items; 1105/1106 and 2333/2337. This is something will have to be corrected by VDOT; the Contractor cannot delete items from the Expedite file. Please advise. (11/14/2016 2:01:06 PM)
A:
Q: Addendum No. 2 did not delete Pay Items 1105 & 1106; Pay Items 2333 & 2337 were added. Both sets of items exist in the Expedite File and on the hard copy of the Schedule of Prices. Please reconcile as required. (11/10/2016 2:50:57 PM)
A:
|
Answer
|
Date:
|
|
|
|
|
Question
|
|
Date:
|
11/16/2016 10:24:07 AM
|
On Plan Sheet 2 N (1); the thickness of the precast garage cladding is shown as 10". Is the 10" thickness the required thickness or is the thickness allowed to vary based on design; please advise.
|
Answer
|
Date:
|
11/23/2016 11:19:31 AM
|
The Contractor is responsible for the final design of the cladding. Panel dimensions provided in the Bid Documents are based on record drawings for the structure. The thickness of the panels may be altered provided that specified requirements are met including review and approval of appearance by VDOT (for example, depth of pattern and compatibility with existing adjacent panels) and structural adequacy is provided and demonstrated.
|
|
|
Question
|
|
Date:
|
11/15/2016 10:46:36 AM
|
Can the Department clarify if the Contractor is to retrofit the existing signal heads with Reflective Backplates at the Scotts Crossing/Jones Branch Drive Signal - Sheet 13(3)1? The other signals within the project limits will be installed or retrofitted with Reflective Backplates.
|
Answer
|
Date:
|
11/16/2016 3:24:49 PM
|
As stated in the notes at the bottom of the drawing, the Contractor shall not retrofit the existing signal heads with Reflective Backplates at the intersection shown on Sheet 13(3)1.
|
|
|
Question
|
|
Date:
|
11/10/2016 11:34:25 AM
|
Have received the notice of the bid date change to November 30, will there be an additional amendment coming with more information ? What is the reason for the bid date change ?
|
Answer
|
Date:
|
11/10/2016 4:11:38 PM
|
None planned at this time.
|
|
|
Question
|
|
Date:
|
11/10/2016 11:34:14 AM
|
Have received the notice of the bid date change to November 30, will there be an additional amendment coming with more information ? What is the reason for the bid date change ?
|
Answer
|
Date:
|
11/10/2016 4:12:38 PM
|
To allow bidders to digest the previous revisions.
|
|
|
Question
|
|
Date:
|
11/9/2016 2:32:11 PM
|
The Washington Gas as-built plans recently retrieved from the Construction Page website is for the work identified as Phase 5. Drainage structures 5-22 and 5-27, MSE Wall RW005, and the proposed soundwall under the Jones Branch Connector all appear to be in conflict with this gas main. Can the As-builts for the gas main identified as Phase 1 with plan and profile be provided ?
|
Answer
|
Date:
|
11/9/2016 3:55:47 PM
|
These are now posted on CABB.
|
|
|
Question
|
|
Date:
|
11/8/2016 1:46:10 PM
|
Can VDOT verify the estimated quantities for the loop detector saw cut?
|
Answer
|
Date:
|
11/14/2016 1:54:13 PM
|
Listed on Page 19 of SOI dated 11/01/2016
|
|
|
Question
|
|
Date:
|
11/5/2016 9:04:34 PM
|
Can the Department please clarify the difference between pay items 1105 & 1106 and 2333 & 2337. They appear to be the same.
|
Answer
|
Date:
|
11/10/2016 9:54:17 AM
|
Pay items 1105 and 1106 should have been replaced by 2333 and 2337 respectively in Addendum #2. Delete pay items 1105 and 1106.
|
|
|
Question
|
|
Date:
|
11/14/2016 2:01:06 PM
|
The new Expedite file that was just posted on Bid Express still contains both sets of items; 1105/1106 and 2333/2337. This is something will have to be corrected by VDOT; the Contractor cannot delete items from the Expedite file. Please advise.
|
Answer
|
Date:
|
11/28/2016 2:44:13 PM
|
Line items 1105 & 1106 are redundant. Please bid $0.00 for both items.
|
|
|
Question
|
|
Date:
|
11/10/2016 2:50:57 PM
|
Addendum No. 2 did not delete Pay Items 1105 & 1106; Pay Items 2333 & 2337 were added. Both sets of items exist in the Expedite File and on the hard copy of the Schedule of Prices. Please reconcile as required.
|
Answer
|
Date:
|
|
|
|
|
Question
|
|
Date:
|
11/4/2016 1:33:47 PM
|
The 2T series of plan sheets indicate numerous pipe plugs to be measured and paid under Concrete Class A3 Misc, the 2016 Road and Bridge standards indicate that pipe plugs associated with abandoned pipe are incidental to and part of the Flowable Fill pay item for pipe abandonment. Please indicate how the Concrete Class A3 will be measured and/or paid regarding pipe plugs for abandoned pipe ?
|
Answer
|
Date:
|
11/10/2016 9:46:44 AM
|
Specific uses for the Class A3 Misc Concrete are described in the comments for the associated row on Sheet 2T. Pipe plugs shall be paid in accordance with the 2016 Specification.
|
|
|
Question
|
|
Date:
|
11/4/2016 1:30:26 PM
|
The 2016 Road and Bridge Standards state that paved ditches (specifically in this case PG-2A) are to be paid by the square yard with a specific PG-2A pay item. There is a significant amount of PG2A on this project with no pay item, however it appears to be accounted for in the Concrete Class A3 Pay item, please confirm that the PG2A will be paid under the Misc Concrete Class A3 Pay item and that the quantities shown in the Drainage Summary sheets ( 2T series) are in fact expressed in "Cubic Yards" as shown versus in square yards which is the typical method of measurement.
|
Answer
|
Date:
|
11/8/2016 4:14:34 PM
|
The referenced PG-2A ditches, are shown as channels CH-57 and CH-59 on Sheet 2T(3). The cost shall be paid Proposal Line # 0090, Bid Item 00525 CONCRETE CLASS A3 MISC. in CY.
|
|
|