Advertisements   Division Home   Bid Results   Bid Tabs   Ad Report   VDOT Forms
Project Info
Order Number UPC State Project Number Last Date to Post Questions
J32 101386 (NFO) 0661-052-750,C501, D629 3/18/2016
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Box Type: Plan
Question Date: 3/21/2016 1:19:35 PM
Can the entire length of the proposed box culvert be pre-cast?  
Answer   Date: 3/21/2016 1:26:21 PM
Yes, the structure length for a pre-cast box would increase to 118’ and would require a 45° skew for the endwall/headwall. VDOT has revised page 3 of the plans. This page is posted under ANNOUNCEMENTS on the Construction Home page. Please also notice these changes: Line Item No. 0450 -6” DI Water Main should be 364LF (vs. 182 LF per plans) ~~~ Line Item No. 0470 – 6” GV should be 4 EA (vs. 2 EA per plans) ~~~ Line Item No. 0480 – 16” Steel Encase Pipe will not be used  
 

Displaying questions 1 - 1 (of 1)
Page: 1 First Previous Next Last