Subject: as built plans Type: Plan
Question Date: 9/18/2014 1:42:21 PM
would you provide the sketches of the existing bridge including the abutments?  
Answer   Date: 9/18/2014 4:02:31 PM
VDOT does not have any as-built plans, but we do have some inspector sketches from structure inspection reports. These will be posted under ANNOUNCEMENTS on the construction website.  
 
Subject: Drilled Shafts Type: Other
Question Date: 9/18/2014 8:21:22 AM
will a trial shaft and/or load test be required on this project?  
Answer   Date: 9/19/2014 9:26:38 AM
Test shafts and load tests are not required.  
 
Subject: Weight of Bridge Type: Other
Question Date: 9/5/2014 7:43:36 AM
Can we get the weight of the superstructure of the current bridge  
Answer   Date: 9/18/2014 7:52:59 AM
VDOT believes the approximate weight to be 55,500 lbs.  
 

Displaying questions 1 - 3 (of 3)