Project Info
Order Number UPC State Project Number Last Date to Post Questions
F12 105584 0007-053-086,C501,B668 8/20/2021
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Low Maint Attenuator Type: Bid Sheet
Question Date: 8/18/2021 9:18:47 PM
Plan sheet 5 depicts the permanent attenuator as LOW MAINTENANCE. The bid item (13607) for this attenuator does not denote low maintenance. What is correct, the bid item as a re-directive only or the plan sheet for low maintenance?  
Answer   Date: 8/24/2021 2:52:46 PM
A LOW MAINTENANCE attenuator is required.  
 
Subject: Storm Run 5-6 to 5-8 Type: Plan
Question Date: 8/18/2021 10:03:40 AM
The storm run shown on Sheet 5 runs through the grass strip between existing sidewalk and curb/gutter. The sidewalk will have to be removed and the curb will most likely be damaged. Where is this work measured and paid?  
Answer   Date: 8/24/2021 2:53:40 PM
Removing and restoring existing surfaces is included in the price of new pipe in accordance with Section 302.04.  
 
Subject: GR 9' Post Requirment Type: Plan
Question Date: 8/17/2021 11:45:41 PM
Plan Sheet 2B depicts 9' post required between Station 106+65 - 104+22, however the pay items depict 6' standard post. Nothing is stated about 9' post under incidentals on page 2. What is correct, the pay items or notes on plan sheet 2B?  
Answer   Date: 8/24/2021 2:54:37 PM
Nine foot posts will be required where the two foot four inch space the GR-MGS1 cannot be provided which is approximately 50 LF along EB Russell Branch Parkway. The discrepancy will be addressed after Contract execution.  
 
Subject: MOT Type: Proposal
Question Date: 8/17/2021 4:12:19 PM
The time for Lane Closures chart on page 240, allows for overnight double lane restrictions to last until 5:00 a.m. The Lane Users fees on Page 242 creates fines past 4:00 a.m. Which chart is correct?  
Answer   Date: 8/24/2021 2:55:06 PM
Allowable lane closure hours are based on the table in the Limitations of Operation special provision not the user fee table.  
 
Subject: Item 0780 PCMS Quantity Type: Proposal
Question Date: 8/17/2021 1:53:20 PM
Bid Item 0780 PCMS has a bid quantity of 3,360 HR. The traffic plans don't show any PCMS boards, please advise where the PCMS signs will be utilized  
Answer   Date: 8/24/2021 2:55:47 PM
The PCMS will be used for lane closure operations (shoulder closure, lane shifts, etc.) and every time the traffic patterns will be changed. The PCMS are to be used on each roadway of this project (Russell Branch and Route 7) for two weeks in advance before any work starts.  
 
Subject: Existing Waterline Material Type: Plan
Question Date: 8/17/2021 10:23:08 AM
What is the existing waterline material where the new water main connections are made? Please provide type of existing pipe for each connection / size of water main.  
Answer   Date: 8/24/2021 2:56:23 PM
The existing water mains within the project limits are believed to be ductile iron, but per general note 1 on sheet 12(2), “The location, depths and sizes of existing utilities shown on the utility adjustment plans are not guaranteed.  The contractor shall field verify with test holes the location, elevation, type, roundness and size of all existing underground utilities and points of connection prior to excavation, ordering materials and installation for this project.”  
 
Subject: 36" Storm Run from EX40 to 5-09 Type: Plan
Question Date: 8/16/2021 1:52:03 PM
On profile sheet 08(13), it states that 100 LF of 36" SSP Required. On plan sheet 5 it shows the 36" run from EX40 to 5-09 as being existing. please clarify which instance is correct.  
Answer   Date: 8/24/2021 2:56:57 PM
The pipe from EX40 to 5-09 is existing. The profile sheet will be addressed after Contract execution.  
 
Subject: PIER PROTECTION SYSTEM BPPS-2 Type: Plan
Question Date: 8/16/2021 8:32:03 AM
54" BPPS-1 shown on Bridge Plan sheet 1 of 49 and detailed on Roadway Plan sheets 2M(2) and 2M(3) does not appear to have any fill material in the space between to two lines of barriers located on the north and south sides of the pier columns. Is it the intent of the Owner to leave this space empty?  
Answer   Date: 8/24/2021 3:00:23 PM
See cross sections 65 to 69 for slopes concerning the area behind the bridge pier protection system.  
 
Question Date: 8/16/2021 8:32:00 AM
54" BPPS-1 shown on Bridge Plan sheet 1 of 49 and detailed on Roadway Plan sheets 2M(2) and 2M(3) does not appear to have any fill material in the space between to two lines of barriers located on the north and south sides of the pier columns. Is it the intent of the Owner to leave this space empty?  
Answer   1 previous answer(s) Date: 8/24/2021 2:59:45 PM
See cross sections 65 to 69 for slopes concerning the area behind the bridge pier protection system.  
 
Question Date: 8/16/2021 8:31:57 AM
54" BPPS-1 shown on Bridge Plan sheet 1 of 49 and detailed on Roadway Plan sheets 2M(2) and 2M(3) does not appear to have any fill material in the space between to two lines of barriers located on the north and south sides of the pier columns. Is it the intent of the Owner to leave this space empty?  
Answer   Date: 8/24/2021 2:59:03 PM
See cross sections 65 to 69 for slopes concerning the area behind the bridge pier protection system.  
 
Subject: Utilities Type: Plan
Question Date: 8/11/2021 10:14:44 AM
How are pipe removals measured and paid?  
Answer   Date: 8/24/2021 3:07:43 PM
Pipe removal is included in the price of new pipe in accordance with Section 302.04.  
 
Question Date: 8/11/2021 10:12:06 AM
There is a Fire Hydrant removal on plan sheet 12(5). How is this measured and paid?  
Answer   Date: 8/24/2021 3:07:15 PM
Removing fire hydrants and other waterline appurtenances is incidental to the price of new water mains in accordance with Section 520.06.  
 
Question Date: 8/11/2021 10:06:28 AM
Plan sheet 12(6) Note 1 involves repair work to an existing Sanitary MH. Where is this item measured and paid?  
Answer   Date: 8/24/2021 3:06:42 PM
Plugging the existing sanitary sewer manhole is incidental to the Flowable Backfill Utility. Shaping the invert in incidental to sewer line installation.  
 
Subject: MSE Modified Moment Slab with Railing Type: Specifications
Question Date: 8/5/2021 12:45:49 PM
Please confirm the MSE modified moment slab w/railing stub wall will require architectural treatment and if so where is that being paid?  
Answer   Date: 8/10/2021 9:01:07 AM
Architectural treatment is required on the outside of the BR-27 railing including terminal walls on the bridge and the MSE moment slabs.  This is paid under Item 62004.  
 

Displaying questions 1 - 10 (of 20)