Subject: Underdrain Type: Plan
Question Date: 6/19/2020 7:53:08 AM
Sheet 5 calls out "UD-7 Ends at Sta. 171+50". This is the only mention of UD-7 in the plans or specifications and the Schedule of Items has no corresponding pay item. Is this a part of the work?  
Answer   Date: 6/23/2020 8:30:55 AM
UD-7 is not part of the work.  
 
Subject: Access Type: Other
Question Date: 6/18/2020 2:06:39 PM
Will the contractor be able to access the work related to Manhole 3A from the cul de sac of Stratton Metals? If not, will the contractor have to access the work from the off ramp of Belvidere to Brook Road?  
Answer   Date: 6/23/2020 8:31:45 AM
Access to the work area should be from I-95.  
 
Subject: Demo of Existing High Voltage Fence Type: Specifications
Question Date: 6/18/2020 1:51:01 PM
Please provide additional details or specifications regarding the removal of the existing high voltage fence.  
Answer   Date: 6/18/2020 5:11:02 PM
The high voltage fence has been relocated outside of the temporary construction easement.  
 
Subject: Sign Posts Type: Specifications
Question Date: 6/18/2020 10:30:00 AM
Plans call out for STP-2 4" posts, yet there isn't a standard STP-2 4" post. The closest post would be a W12x19 according to the panel size. Please clarify which post is to be used.  
Answer   Date: 6/18/2020 5:09:02 PM
The STP-2 standard was updated and re-activated in August 2019 in the VDOT 2016 Road and Bridge Standards. Please refer to VDOT Standard series 1321.xx for details on posts and foundations.  
 
Subject: Foundation Design for Signs Type: Specifications
Question Date: 6/18/2020 10:27:44 AM
The plans call out for a 2'x6' foundation for the signs on sheet 6(2B), but there isn't a standard VDOT foundation of that size. Please clarify which standard foundation is to be used.  
Answer   Date: 6/18/2020 5:09:35 PM
The STP-2 standard was updated and re-activated in August 2019 in the VDOT 2016 Road and Bridge Standards. Please refer to VDOT Standard series 1321.xx for details on posts and foundations.  
 
Subject: Median Widening Type: Plan
Question Date: 6/18/2020 8:48:29 AM
On Sheet 2(A) Median Widening is shown through station 158+90. On Plan Sheet 3 there is no hatching showing this median work. Can you please confirm the correct stations where this work will occur?  
Answer   Date: 6/23/2020 8:31:31 AM
The median widening through sta. 158+90 will be a 5" mill & overlay. The proposed change will be handled through the change order process after award.  
 
Question Date: 6/15/2020 10:13:48 AM
On the full depth section located in the median between stations 153+67 to 161+67 the excavation and replacement is 22" deep. Does the Department intend to utilize temporary concrete barrier service to protect this work zone? Given the lane closure time of 9:30 to 5:30 there is not enough time for excavation, placement of stone and the multiple lifts of asphalt required (including curing time required between lifts)  
Answer   Date: 6/18/2020 5:12:04 PM
The Department intent is not to have a proposed 22" deep section in the location in question. Instead a 5" mill & overlay will take place in the specified location. The proposed change will be handled through the change order process after award.  
 
Subject: In Ground Conflicts Type: Plan
Question Date: 6/18/2020 7:46:20 AM
Can as-builts of the existing Belvidere St bridge be provided so that the contractor can determine if potential conflicts exist between the required excavation for proposed structure MH 3A and the footer of the existing wall and/or abutment footing?  
Answer   Date: 6/23/2020 9:20:02 AM
The as-built plans are available on ProjectWise.  
 
Subject: Existing Sign Removal Type: Bid Sheet
Question Date: 6/17/2020 4:04:38 PM
There are signs to be removed but no pay item, please clarify how the removal of signs will be paid for.  
Answer   Date: 6/23/2020 9:02:14 AM
Please see the note on sheet 6(1): "Signs noted on plans to be removed that do not have an accompanying sign label shall not be measured separately for payment. Removal and disposal for such signs shall be incidental to other contract items." These would be the signs within the cut and fill line, or clearing and grubbing areas.  
 
Subject: Geotech Type: Other
Question Date: 6/16/2020 9:56:16 AM
Is a geotechnical report available for the deep manhole locations? Structures MH 3A and MH 5A  
Answer   Date: 6/18/2020 5:10:34 PM
A geotechnical report is not available for the location in question .  
 