Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
B62
110951
0734-038-780, B652
10/18/2019
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Plan Sheet 10A
Type:
Plan
Question
Date:
9/11/2019 8:55:18 AM
Plan Sheet Status is "Checked In" as opposed to "Final". The PDF cannot be opened.
Answer
Date:
9/13/2019 11:32:13 AM
Plan sheet is now marked as Final.
Question
Date:
9/30/2019 4:00:42 PM
Pay item 68490; Disposal of Material Str. No. 6084 Ty B. We would like to have existing bridge information. I believe Ty B refer to Lead contain material and dispose as accordingly. Please provide more information.
Answer
Date:
10/2/2019 10:00:27 AM
Structure is classified as a Type B structure which may have existing coatings contain hazardous materials. Pay Item 68490 is intended for disposal of any hazardous materials. See section 411 of Specifications for descriptions. Existing bridge plans do not exist.
Question
Date:
9/30/2019 3:58:44 PM
Can we substitute Dewatering Basin EC-8 for Dewatering Bag?
Answer
Date:
10/2/2019 10:02:25 AM
No
Question
Date:
9/30/2019 2:47:10 PM
There is a pay item for Temporary Bridge and shown in the contract proposal page 147&149 but not much in detail. What is VDOT expectation/intent to have temporary work bridge. Demolition middle pier? Also demolition of middle pier how deep we need to remove the existing pier? Please provide specific information.Not much information about bridge abutments reconstruction. Please provide all details information.
Answer
Date:
10/2/2019 10:22:38 AM
Intent for temporary work bridge is for removing existing pier. Pier shall be removed a minimum of 1' below steam bed. Its at the contractors discretion of how temporary bridge will be constructed. Abutment footings and wingwalls shall be designed by contractor specific to the precast structure that will be used. Foundation elevations and geology findings are provided in plans for design purposes. VDOT isn't allowed to call out specific manufacturer of precast structure so footings and wingwalls will need to be designed per manufacturers dimensions and design calculations of structure.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/26/2024 12:03:01 PM
2008