Project Info
Order Number UPC State Project Number Last Date to Post Questions
B60 113639 9999-964-583,B618-620,C501 11/8/2019
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Demolition of Pavement Type: Proposal
Question Date: 11/7/2019 11:28:19 AM
Is Demolition of Pavement and/or Milling that is required for the shoulder strengthening included in the bid item for Asphalt Concrete Ty SM-19.0D(T)?  
Answer   Date: 11/8/2019 3:16:38 PM
Trenching is included in the pay item for SM 19.0D(T) and shall be performed in accordance with Section 315.05 of the Special Provision for TRENCH WIDENING ASPHALT MIXTURES SM-19.0D(T)  
 
Subject: Measurement of Latex Mod. Concrete Type: Plan
Question Date: 11/7/2019 11:04:46 AM
Plan sheet 3 for the Dinwiddie bridges states that Furnish Very Early Strength Latex Modified Concrete will be paid for on the basis of plan quantity. Is this correct? The furnish quantity can be highly variable based on the condition of the existing deck and how much concrete is removed during hydro-demolition.  
Answer   Date:
 
 
Subject: Revised Plan Sheets Type: Plan
Question Date: 11/4/2019 3:37:47 PM
Please make the latest revised plan sheets available on Project Wise.  
Answer   Date:
 
 
Question Date: 10/16/2019 2:16:12 PM
The Revision Letter dated 10/16/2019 indicates that plan sheets 187-04B and 188-01A have been revised. All of the plan sheets for structure B620 are labeled 187-04B and none of them indicate in their revision block that they have been revised. Additionally, the Table of Revisions is blank. Please clarify which plan sheets have been revised for both 187-04B and 188-01A  
Answer   Date: 10/16/2019 5:21:23 PM
The files have been updated in ProjectWise.  
 
Subject: Rumble Strip Removal Type: Proposal
Question Date: 10/18/2019 7:30:27 AM
Does the bid item for Remove Exist. Rumble Strip include placement of asphalt, or is asphalt paid for separately? What type of asphalt should be used?  
Answer   Date:
 
 
Subject: MB-11A Type: Other
Question Date: 10/17/2019 3:44:43 PM
Per VDOT MB-11A Standard, all MB-11A on bridge decks will be bolted down and all MB-11A on roadways will be pinned. Please confirm that all barrier for this project will be either bolted or pinned depending upon its location..  
Answer   Date: 10/18/2019 5:28:04 PM
Yes, the barrier for this project will be either bolted or pinned depending upon its location in accordance with the 2016 VDOT Road and Bridge Standards.  
 
Subject: TMA Type: Bid Sheet
Question Date: 10/11/2019 3:03:04 PM
It appears that the number of hours in the schedule of items for the TMA may not be sufficient to provide maintenance of traffic according to the Work Area Protection Manual for the proposed maintenance activities. Would the Department consider adding TMA hours to the proposal?  
Answer   Date: 10/11/2019 3:03:26 PM
An addendum will be forthcoming to adjust the total TMA hours from 32 to 362.  
 
Subject: Asbestos Report Type: Other
Question Date: 10/9/2019 9:30:09 AM
Will an asbestos report be made available before the bid? General location and scope would go along ways in getting a best price.  
Answer   Date: 10/10/2019 8:08:28 AM
The asbestos report is located in the Projectwise folder titled Asbestos Report.  
 

Displaying questions 1 - 7 (of 7)