Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
B50
114881
SN05-965-364, N501
8/16/2019
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Wood Post
Type:
Bid Sheet
Question
Date:
8/9/2019 9:43:51 AM
The wood post quantities are only 2 lf of each, is this correct? If so, can you explain what the 2 lf of each post will be used for?
Answer
Date:
8/9/2019 4:22:34 PM
Quantities have been revised. Please see the latest SOI.
Subject:
Summary of Quantities
Type:
Proposal
Question
Date:
8/9/2019 9:41:58 AM
The summary of quantities beginning on page 283 only shows 13 of the 73 line items. Will the contractors be provided summary of quantities of locations for the remaining items?
Answer
Date:
8/9/2019 3:20:04 PM
This is only showing what the estimated quantities are for that particular task order. Only those 13 line items are being utilized for that particular task order.
Subject:
Remove Concrete Foundation
Type:
Bid Sheet
Question
Date:
8/9/2019 9:37:32 AM
There are only two each of the O/H sign structure foundation and two of the ground mount concrete foundation. The quantities are less than the removal of signs. Can you clarify what signs that the remove foundations go with? How is the contractor going to be paid for the additional foundation removals?
Answer
Date:
8/9/2019 3:16:31 PM
These line items are for the O/H or Ground Mount Structure Foundation removals only. These are proposed for locations where the sign panels and post/structures were previously removed by other sources. Please refer to the special provision located on page 4. Any additional foundation removals are included within Remove Existing Sign Structure (Ty. XX), refer to Spec 700.06 in the 2019 Supplement to the 2016 Road and Bridge Specifications.
Subject:
Flagging Operations
Type:
Specifications
Question
Date:
7/30/2019 1:08:07 PM
Due to the recent changes will temporary rumble strips need to be added to the contract?
Answer
Date:
8/6/2019 8:57:41 AM
Portable Temporary Rumble Strips will be added via addendum this week.
Displaying questions 1 - 4 (of 4)
Page: