Order Number
UPC
State Project Number
Last Date to Post Questions
B33
95112
0015-023-719, B617
8/16/2019
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Existing Shear Studs
Type:
Plan
Question
Date:
8/16/2019 11:51:28 AM
Please confirm if there are shear studs present on the existing stringers.
Answer
Date:
8/19/2019 3:49:31 PM
Shear studs are not present on the top flanges of the existing stringers.
Subject:
Fracture Critical Members
Type:
Plan
Question
Date:
8/15/2019 2:12:45 PM
On sheet 2 in the general notes it states all steel repairs occurring in Fracture Critical Areas must conform to the AASHTO Fracture Control Plan. No local AISC shops have this endorsement. As long as the material and its fabrication conforms to FCP guidelines will VDOT waive the FCP endorsement requirement?
Answer
Date:
8/19/2019 3:48:53 PM
No, VDOT will not waive the FCP endorsement requirement.
Subject:
Concrete Repairs
Type:
Plan
Question
Date:
8/15/2019 1:58:06 PM
Per 412.03 (g) shotcrete is allowed when approved in writing. Would vdot allow the beams and substructure repairs to be completed utilizing shotcrete instead of scc?
Answer
Date:
8/19/2019 3:50:06 PM
No.
Subject:
Drainage inlet
Type:
Plan
Question
Date:
8/15/2019 12:21:13 PM
What is the length of the shear connectors on the drainage inlet? Is the Top of said inlet meant to be removable?
Answer
Date:
8/19/2019 3:50:43 PM
The drainage inlet 1/2" diameter studs are to be 4" long. The top of the inlet is not meant to be removable.
Question
Date:
8/15/2019 11:39:13 AM
What is the length of the shear connectors on the drainage inlet? Is the Top of said inlet meant to be removable?
Answer
Date:
8/19/2019 3:50:52 PM
The drainage inlet 1/2" diameter studs are to be 4" long. The top of the inlet is not meant to be removable.
Subject:
curb
Type:
Plan
Question
Date:
8/14/2019 4:04:13 PM
Plan sheet 13 of 15 indicates the limits of the removal of the curb. In regards to this: 1) where there is not a drain area does the removal go full depth to the top of the deck? 2) Where the curb is completely deteriorated how is the full width replacement paid for?
Answer
Date:
8/19/2019 3:51:50 PM
1) As shown in the plans, the removal of the curb at the posts was not intended to go down to the top of slab. 2) The full width of the curb is not intended to be replaced.
Subject:
Latex modified concrete
Type:
Plan
Question
Date:
8/14/2019 1:50:52 PM
Can silica Fume be substituted for latex modified concrete?
Answer
Date:
8/19/2019 3:52:17 PM
No.
Subject:
decking
Type:
Plan
Question
Date:
8/14/2019 1:50:14 PM
Are SIP forms allowed for decking?
Answer
Date:
8/19/2019 3:52:53 PM
SIP forms are allowed for decking in Spans 2 and 3. The design load includes 20 psf allowances for construction tolerances and construction methods.
Subject:
platform
Type:
Plan
Question
Date:
8/14/2019 1:49:50 PM
The existing platform and unknown box is in poor shape. Is this to be removed and replaced? Restored or just removed?
Answer
Date:
8/19/2019 3:53:52 PM
The intent is for the existing platform to remain in place. If repairs described in the plan set cannot be accomplished with the platform in place, the contractor shall remove and re-install in kind after said work is complete.
Subject:
Type:
Plan
Question
Date:
8/14/2019 1:48:57 PM
The plans indicate that L2U3 on the downstream side is to be repaired. The upstream side is also damaged. Is the intent of the department to repair this member also?
Answer
Date:
8/19/2019 3:54:32 PM
The plans indicate that L2U3 and U3L4 on the downstream truss in Span 3 are the only diagonal members to be repaired.
Question
Date:
8/14/2019 1:48:54 PM
The plans indicate that L2U3 on the downstream side is to be repaired. The upstream side is also damaged. Is the intent of the department to repair this member also?
Answer
Date:
8/19/2019 3:54:45 PM
The plans indicate that L2U3 and U3L4 on the downstream truss in Span 3 are the only diagonal members to be repaired.
Subject:
Rails
Type:
Plan
Question
Date:
8/14/2019 1:47:28 PM
It appears the intent is to use the existing posts in span 1 and 4 and just replace the rails is this correct?
Answer
Date:
8/19/2019 3:55:23 PM
The posts were not intended to be replaced.
Displaying questions 1 - 10 (of 15)
Page:
1
2
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/26/2024 8:00:23 PM
2008