Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
U68
108897
0058-044-039, N501
6/21/2019
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Drainage Summary & Drainage Descriptions
Type:
Plan
Question
Date:
5/17/2019 9:45:12 AM
There is no structure information for structures 3-1, 3-2, 3-3, 3-4, 3-5, 3-6, or 3-7. Will this information be provided via drainage descriptions and/or drainage summary or both?
Answer
Date:
6/11/2019 4:43:21 PM
Drainage Descriptions are included in the June 11, 2019 Revision.
Subject:
Borrow Material
Type:
Proposal
Question
Date:
5/17/2019 9:29:18 AM
Grading is lump sum. It appears to be a lot of borrow Material needed for the project. Is this borrow suppose to be included in the lump sum. If so what are the CBR requirements, etc. There is no drainage detail sheet. Proposal does not have any details on the three MH structures or Frame & Covers
Answer
Date:
6/11/2019 4:43:08 PM
This is a No Plan project where borrow is to be included in the cost of Grading, as per 2016 VDOT Road and Bridge Specification Section 303.06(f.) and Project Note No. 19. Grading Note G-6 specifies CBR-5.0. Drainage Descriptions are included in the June 11, 2019 Revision.
Displaying questions 1 - 2 (of 2)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/26/2024 9:53:35 PM
2008