Project Info
Order Number UPC State Project Number Last Date to Post Questions
U68 108897 0058-044-039, N501 6/21/2019
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Drainage Summary & Drainage Descriptions Type: Plan
Question Date: 5/17/2019 9:45:12 AM
There is no structure information for structures 3-1, 3-2, 3-3, 3-4, 3-5, 3-6, or 3-7. Will this information be provided via drainage descriptions and/or drainage summary or both?  
Answer   Date: 6/11/2019 4:43:21 PM
Drainage Descriptions are included in the June 11, 2019 Revision.  
 
Subject: Borrow Material Type: Proposal
Question Date: 5/17/2019 9:29:18 AM
Grading is lump sum. It appears to be a lot of borrow Material needed for the project. Is this borrow suppose to be included in the lump sum. If so what are the CBR requirements, etc. There is no drainage detail sheet. Proposal does not have any details on the three MH structures or Frame & Covers  
Answer   Date: 6/11/2019 4:43:08 PM
This is a No Plan project where borrow is to be included in the cost of Grading, as per 2016 VDOT Road and Bridge Specification Section 303.06(f.) and Project Note No. 19. Grading Note G-6 specifies CBR-5.0. Drainage Descriptions are included in the June 11, 2019 Revision.  
 

Displaying questions 1 - 2 (of 2)