Project Info
Order Number UPC State Project Number Last Date to Post Questions
B10 109130 0064-002-926, B616, B617, B618 5/17/2019
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Weekend Closures and Detours Type: Proposal
Question Date: 5/9/2019 3:01:06 PM
VDOT Notice dated May 9, 2019 deleted the times that the weekend closures and detours on I-64 Eastbound and Westbound are permitted. To properly prepare our bid we need to know when we will be allowed to setup these closures/detours and when we have to have them removed. Can you re-establish the time frame when these closures/detours will be permitted?  
Answer   Date:
 
 
Subject: Proposal Line Number 0150 Type: Proposal
Question Date: 5/1/2019 9:49:01 AM
Proposal Line Number 0150, FURNISH LATEX MODIFIED CONC. VERY EARLY STRENGTH 4” & VAR, has a bid quantity of 47 CY, this quantity is way short of the quantity required for 5,380 SY of overlay. Should this items quantity be adjusted?  
Answer   Date: 5/3/2019 2:37:46 PM
Yes. A revision will be posted reflecting the correct quantity.  
 
Subject: Bridge Approach Slabs Type: Proposal
Question Date: 4/30/2019 10:46:30 AM
Does the quantity of 5,380 SY include the bridge approach slabs or only the bridge deck?  
Answer   Date: 5/3/2019 2:37:09 PM
The bridge deck only.  
 
Question Date: 4/30/2019 10:48:06 AM
Do the bridge approach slabs receive a Latex Modified Concrete Overlay?  
Answer   Date: 5/3/2019 2:36:49 PM
No, only the bridge deck.  
 
Subject: Plans and Proposal Type: Proposal
Question Date: 4/9/2019 4:32:53 PM
When will the plans and proposal be available to print on Project Wise?  
Answer   Date: 4/10/2019 2:18:06 PM
The proposal is available in ProjectWise and contains the No-Plan Assembly  
 

Displaying questions 1 - 4 (of 4)