Subject: Temporary Construction Signs Type: Proposal
Question Date: 5/16/2019 12:02:25 PM
Where is the Temporary Construction Sign Schedule (layout) for this project?  
Answer   Date: 5/17/2019 12:17:51 PM
Per the No Plan Assembly, the Temporary Traffic Control (TTC) references are 5.1, 23.1, 28.1 and 53.0 in the Virginia Work Area Protection Manual, 2011 version, revised April 1, 2015.  
 
Subject: Widening Type: Proposal
Question Date: 4/25/2019 11:36:16 AM
The typical section on Page 106 of the proposal states that total trench widening shall be 3' wide. The 2nd paragraph on Page 107 states that the shoulders shall be paved up to two feet. Recognizing that there are areas where widening will be limited, is the general expectation to widen two feet on both sides of the road?  
Answer   Date: 4/29/2019 3:27:25 PM
The trenching operation will be 3' in total width. The width of the trenching operation outside of the the existing edge of pavement will vary between 1' & 2' at locations noted in the NPA. The remainder of the 3' width will be performed within the existing travel lane.  
 
Question Date: 5/13/2019 8:41:27 AM
BM-25T asphalt is called to be installed 5" depth x 1' to 2' width What are the asphalt density requirements for the BM-25T asphalt installed?  
Answer   Date: 5/14/2019 3:02:11 PM
Density will be enforced in accordance with the requirements in SP 315 Trench Widening Asphalt Mixtures.  
 

Displaying questions 1 - 2 (of 2)