Project Info
Order Number UPC State Project Number Last Date to Post Questions
N77 109272 (NFO)0621-053-158,C501 4/19/2019
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: AASHTOWare bidding software files. Type: Other
Question Date: 4/18/2019 12:56:45 PM
As of today, there are no AASHTOWare files available for this project on either the CABB site or the ProjectWise web server. The These files are required to bid on projects through the new AASHTOWare bid software being used, and Virginia Department of Transportation no longer will no longer accept bids from the Expedite software which was used previously for electronic bidding. When and where will the AASHTOWare files required for electronically bidding on this project be made available?  
Answer   Date: 4/19/2019 9:55:04 AM
Those files are located on Bid Express and can be downloaded from there.  
 
Subject: Item 0330 - Group 2 Channelizing Devices Type: Bid Sheet
Question Date: 4/16/2019 2:06:01 PM
Item 0330 - Group 2 Channelizing Devices is given with a quantity of 11,340 and in units of Day. As this item corresponds to MOT barrels, the quantity and units shown on the bid sheet don't appear to be sensible. Please advise.  
Answer   Date: 4/19/2019 9:48:24 AM
The Group 2 Channelizing Devices quantity and units shown are reasonable for the timeframe and length of this project.  
 
Subject: Demo. of Bldg. Parcel 003, D900 Type: Bid Sheet
Question Date: 4/16/2019 11:48:03 AM
The Demo. of Bldg. Parcel 003, D900 is listed as Item 0650 on the bid sheet as a lump sum item, but the only reference to it on the plans is on Sheet 23 of the construction drawings under Demolition of Buildings, and the description given there is Sewage Drain Field at Station 308.90 RT. Is this actually an excavation item, and not a building demolition? Please advice.  
Answer   Date: 4/19/2019 9:50:24 AM
The D900 refers to an abandoned sewage drain field to be removed within the construction limits. It is also referred to on sheet 2A (Typical Section), sheet 2B (Grading Diagram, note 13) and on cross section sheet 3.  
 
Subject: Pipe materials. Type: Specifications
Question Date: 4/15/2019 11:58:46 AM
What materials are line items 0120 - 15" Pipe, 0130 - 18" Pipe, and 0140 - 30" Pipe, on the Schedule of Items comprised of? The materials do not appear to be listed in any of the project documents.  
Answer   Date: 4/19/2019 9:47:47 AM
Line items 0120-15” pipe and 0130-18” pipe can use any material accepted in allowable pipe chart located on plan sheet 2C. Item 0140-30” pipe will be concrete material and will require use of ES-1 end section.  
 
Subject: Geotechnical Report Type: Other
Question Date: 4/9/2019 8:15:50 AM
Is the Geotechnical report available for the project?  
Answer   Date: 4/12/2019 11:09:59 AM
The report has been uploaded into ProjectWise for viewing.  
 
Subject: Allowable lane closure hours Type: Specifications
Question Date: 3/20/2019 9:59:19 AM
Please provide the special provision for allowable lane closures.  
Answer   Date: 4/10/2019 2:54:51 PM
This has been addressed in Revision 1.  
 
Subject: Completion date Type: Proposal
Question Date: 3/20/2019 8:27:54 AM
Please confirm the project completion date of June 1, 2020 as shown on the proposal. The substantial completion date is May 8, 2019.  
Answer   Date: 4/10/2019 2:54:02 PM
This has been addressed in Revision 1.  
 

Displaying questions 1 - 7 (of 7)