Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
A03
101042
(NFO)0778-005-645, C501, B659
11/9/2018
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Construction Surveying
Type:
Bid Sheet
Question
Date:
11/8/2018 3:24:33 PM
There is not a pay item for Construction Surveying on the Schedule of Items. Is VDOT planning to provide the Construction Surveying for this Project?
Answer
Date:
11/8/2018 8:17:24 PM
The Department will provide construction surveying for this project.
Subject:
Bid Item No. 54512-Type D Class II Temp Pvmt Mrkg 4" Quantity
Type:
Bid Sheet
Question
Date:
10/31/2018 3:13:34 PM
Bid Item No. 54512 calls for 3200.00 lf Type D Class II Temp Pvmt Mrkg 4". Being as the portions of Rte 778 and Rte 617 within the project limits are being closed during construction, where does the Department anticipate the Temporary Pavement Markings 4" being located?
Answer
Date:
11/1/2018 10:26:11 AM
The road will be opened prior to all work being completed due to the substantial completion date on page 3 of the proposal requiring temporary pavement markings for traffic control.
Subject:
Permit for Cofferdam and Pier Demo
Type:
Permits
Question
Date:
10/31/2018 3:09:03 PM
The Permit Sketches do not show a Cofferdam or make allowance for isolating the existing pier closest to Abutment A from the stream during demolition and removal. How does the Department anticipate this portion of the work being executed in compliance with the Permit?
Answer
Date:
11/1/2018 10:25:00 AM
The operations proposed by the Permit Sketches are to install the temporary causeway from the river bank on the Abutment B side of the river out to the existing pier and remove the pier. Debris from the pier can be pulled back onto the causeway during the removal. Once the existing pier is removed the causeway would be removed and the temporary cofferdam would be installed prior to excavation operations for the new pier footing.
Subject:
Existing Bridge Plans
Type:
Other
Question
Date:
10/31/2018 9:08:50 AM
Please provide access to Existing Bridge Plans, thank you!!
Answer
Date:
11/1/2018 10:25:36 AM
Existing plans have been uploaded to ProjectWise Web Server.
Displaying questions 1 - 4 (of 4)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/25/2024 7:36:55 PM
2008