Project Info
Order Number UPC State Project Number Last Date to Post Questions
N01 93077 (NFO)0064-121-195,C501, B635 12/14/2018
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: GRG Gasoline Resistant Geomembrane Type: Bid Sheet
Question Date: 12/13/2018 11:59:48 AM
The Bid Schedule unit of measurement for Item 0080 is square yards (SY).. However, the GRG Spec Provision states it "will be measured in square feet and will be paid at the contract square foot price". Please verify per SY is acceptable per the Bid Schedule, or revise the Bid Schedule to reflect SF quantities.  
Answer   Date: 12/18/2018 9:28:13 AM
The unit listed for item 0080 – Geotextile Gasoline Resistant Geomembrane under the Statement of Items of SY shall govern per Section 105.12 of the Specifications. The SF unit item listed in the SP is incorrect.  
 
Question Date: 12/13/2018 11:59:45 AM
The Bid Schedule unit of measurement for Item 0080 is square yards (SY).. However, the GRG Spec Provision states it "will be measured in square feet and will be paid at the contract square foot price". Please verify per SY is acceptable per the Bid Schedule, or revise the Bid Schedule to reflect SF quantities.  
Answer   Date: 12/18/2018 9:28:22 AM
The unit listed for item 0080 – Geotextile Gasoline Resistant Geomembrane under the Statement of Items of SY shall govern per Section 105.12 of the Specifications. The SF unit item listed in the SP is incorrect.  
 
Subject: Excavation for rip rap item # 2040 Type: Bid Sheet
Question Date: 12/13/2018 7:30:48 AM
How is the excavation required for item 2040 - dry rip rap A1 20" - 2641 tons , to be paid? It does not appear in the cross sections or to be captured in regular excavation (bid item 0050), or to be captured with the structure excavation item (bid item 1920). Please advise or update quantities accordingly.  
Answer   Date: 12/18/2018 9:27:33 AM
Per Section 414.04 of the Specification, the price for Item 2040 – dry rip rap A1 20“ shall include excavation. The excavation includes removal of all material required to install riprap and grade adjacent to riprap at Abutment A (below and adjacent to spans a and b) per Contract Documents; incidental excavation quantity is estimated as 4950 CY. For further clarification, the excavation required for the installation of the Item 2050 – Concrete slab slope protection 4” at Abutment B (below and adjacent to span f) shall be included in Item 2110 – Dism & Rem. Ex. Str. 2222; incidental excavation quantity is estimated as 1850 CY.  
 
Subject: Grading Diagram Type: Plan
Question Date: 12/12/2018 3:12:45 PM
Would the Dept provide a Grading Diagram which shows where the quantities in the Grading Summary come from, and where the onsite excavation is to be used?  
Answer   Date: 12/18/2018 9:21:16 AM
Grading diagram is not available.  
 
Subject: Completion date / Incentive date Type: Proposal
Question Date: 12/12/2018 12:40:04 PM
Are you going to extend the completion date and incentive and disincentive dates?  
Answer   Date: 12/13/2018 10:51:39 AM
The project currently has a delayed NTP. The completion and disincentive dates will remain unchanged.  
 
Subject: Pavement Demo Quantites Type: Proposal
Question Date: 11/10/2018 1:02:06 PM
The soil borings show existing asphalt thickness of 24” – 60”+ on each side of the existing bridge. Please verify that this demolition of asphalt must be included in Bid Item 900 – “Demo of Flexible Pavement”?  
Answer   Date: 11/16/2018 9:26:15 AM
Demolition of the full depth of asphalt pavement thickness must be included in Bid Item 900.  
 
Subject: Modular Retaining Wall Type: Plan
Question Date: 11/9/2018 5:12:53 PM
The back of the modular retaining wall system extends beyond the benched excavation limits shown in the plans and cross sections, and results in additional excavation. Does this additional area need to be backfilled with Select Material and/or EPS Fill?  
Answer   Date: 11/29/2018 11:59:03 AM
For the additional excavation that is required for the bottom wall modules beyond the benched excavation shown on the Plans, the Contractor shall reuse the existing material. For wall backfill, please see Geotechnical Details on sheets 2A(3) thru 2A(6).  
 
Question Date: 11/12/2018 8:37:20 AM
Please confirm that the distance "B" shown on sheets 126 and 127 of the bridge applies to the entire height of the wall. In other words, please confirm the select material Type 1 or Type 2 incidental to the retaining system is a vertical line based on distance "B", or is what is incidental step in as the stems from the wall panels step in?  
Answer   Date: 11/29/2018 11:59:41 AM
Non-EPS geofoam backfill material used within minimum wall base width (or B min.) and entire wall height is considered incidental to the precast modular retaining wall structure. Refer to Section 5.0 of Precast Modular Retaining Structure Special Provisions and notes in Sheet 126.  
 
Subject: EPS Type: Other
Question Date: 11/9/2018 3:50:05 PM
Would the Department consider substituting poured in place lightweight cellular concrete in lieu of EPS blocks?  
Answer   Date: 11/13/2018 9:37:57 AM
Lightweight cellular concrete will not be considered in lieu of EPS blocks.  
 
Subject: Vibration Monitoring Type: Specifications
Question Date: 11/9/2018 10:05:45 AM
Under the Measurement and Payment section of the Special Provision for Vibration Monitoring it states that 50% of the lump sum price will be made upon receipt of all Release of Liability letters by the Engineer. Release of Liability letters are not addressed anywhere else within the Special Provision. Please provide further information on what exactly is required for these letters, and who is to provide them.  
Answer   Date:
 
 
Subject: Pier 5 Column Spiral Reinforcin Type: Plan
Question Date: 11/9/2018 9:54:23 AM
Can the #4 CRR I for Pier 5 Column Spirals be changed to individual #4 Hoops with a 1'-11" lap spaced at the pitch spacing of 12"? The #4 CRR I in coil to make spirals is not available at this time.  
Answer   Date: 11/29/2018 12:02:12 PM
No it cannot be changed, further a CRR Class I material supplier for the region indicates that there is no availability issue with the #4 for the spirals. .  
 
Subject: PDA Testing Type: Bid Sheet
Question Date: 11/8/2018 3:21:03 PM
Item 1950 quantity is incorrect. There is only 1 test pile at abutment 1 and b, and only 1 test pile at piers 2 and 5.  
Answer   Date: 11/29/2018 12:03:01 PM
On sheet 4 of 127 there are two stars next to the Dynamic Pile Test item.  Please see the double star note on this sheet for an explanation of the additional test locations.  The quantity for item 1950 is correct.  
 
Question Date: 11/30/2018 9:15:15 AM
Does this mean that there are 5 additional PDA tests on the piles or is there another test pile program with additional pile lengths? If an additional test pile program is required, it appears that the quantity for Bid Item 1970 is wrong.  
Answer   Date: 12/4/2018 9:16:13 AM
Plans indicate locations of test piles which also receive dynamic pile testing. These test piles are paid for as driving test for pile (LF) and Dynamic Pile Test (EA). The plan quantity for Dynamic Pile Test (EA) accounts for an additional 4 tests on piles that are not “test piles” as required by the Engineer. There are no additional test piles.  
 