Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
A08
114355
0664-121-319, C501
10/19/2018
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Asphalt patching
Type:
Specifications
Question
Date:
10/12/2018 3:54:32 PM
Can asphalt patching material be placed without the joint that is shown between them?
Answer
Date:
10/17/2018 10:52:56 AM
Yes, asphaltic matching material may be placed all at one time if permissible by manufacturer’s recommended installation instructions. Consult with the manufacturer’s recommended lift thicknesses for placement.
Question
Date:
10/12/2018 3:53:49 PM
Is the asphalt patching material the same for the joint as well as the roadway?
Answer
Date:
10/17/2018 10:51:54 AM
Yes, asphaltic patching material is the same for joint and roadway.
Subject:
Plan 257-06B
Type:
Plan
Question
Date:
10/12/2018 3:52:57 PM
Plan 257-06B We are concerned about the irregular size of the existing joints as well as location of the existing rebar. The 6” width at the top and the 4” width at the bottom may cause problems with the saw cutting. We request making the joints wider ( maybe 8”) to get away from existing joints which will give a cleaner straight joint. We also request eliminating the “T” at the top and making the joint the same width top to bottom.
Answer
Date:
10/17/2018 10:50:21 AM
The bottom trench width needs to remain 4” wide so the 3” stainless steel bent plate will stay centered over the expansion/contraction joint. The 6”± deteriorated repair joint shown to be demolished should be removed in its entirety. If required to accomplish that, the width of the upper portion can be increased to 8” with no additional costs for extra saw cutting or extra patching material.
Subject:
Ref lane closures
Type:
Specifications
Question
Date:
10/12/2018 3:50:45 PM
Can we work in one lane on both S Island and N Island at the same time? Can we work on inside lanes both N bound and S bound at the same time? ( IE- one lane in each direction closed)
Answer
1 previous answer(s)
Date:
10/17/2018 10:48:23 AM
Yes, the contractor can work in one lane (same lane) on both the South Island and North Island at the same time contingent on scheduling approval in LCAMS. Yes the contractor can work on both Northbound and Southbound lanes at the same time contingent on scheduling approval in LCAMS. It should be noted that the work at MMMBT competes with HRBT and JRB (Same Direction). It would be expected that the contractor work with Tunnel Maintenance personnel and other contractors attempting to get work done at the three facilities and be prepared to work in a different direction in some cases to allow everyone to work together.
Subject:
Pipe Depth
Type:
Plan
Question
Date:
10/4/2018 1:47:33 PM
Please provide depth and type of material of existing longitudinal pipes to be cored, or provide a copy of the as-built plans.
Answer
Date:
10/9/2018 2:04:53 PM
The existing pipe type may be fiberglass or steel. As-built plans do not exist, but record plans indicate the invert of the existing longitudinal drain is at a depth of 3 ft 2 inches from the surface
Subject:
Asphaltic Patching Material
Type:
Specifications
Question
Date:
10/3/2018 8:25:51 AM
It is my understanding that water activated material can be 3 times more expensive than other cold mix materials. The warranty claims the material will survive at least 12 months. There are cold mixes on VDOT Approved List #78 with equal warranties that are significantly lower in cost. Some have been extensively tested throughout the US, including the SHRP federal highway study. The high survivability was demonstrated. Why was this spec written to sole-source only 1 material from Approved List #78 when there are other VDOT Approved options that have demonstrated equal survivability?
Answer
Date:
10/5/2018 9:36:27 AM
The Water Activated Asphaltic Patching Material Specification defines the requirements and allowable thresholds for the referenced material. Any product that meets the performance requirements as specified will be acceptable for use on this project. The material in question is not a sole sourced product.
Displaying questions 1 - 5 (of 5)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/19/2024 10:02:37 AM
2008