Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
N70
107072
(NFO)0460-013-935,N501
6/15/2018
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Typical Section
Type:
Proposal
Question
Date:
6/11/2018 10:37:02 AM
According to the typical section in the proposal the shoulder width to be done is between 2' and 4'. In the areas where 2' is utilized, (some areas this is going to put the edge of the shoulder right at the face of existing guardrail,) is the rumble strip going to be eliminated? The machine requires at least 36" to be able to cut the strips, and even at that there are places that is not enough room. Also the specs require a minimum of 4' for rumble strips to be applied. The proposal does not show at this time that the strips are to be eliminated on any of the shoulder to be placed.
Answer
Date:
6/14/2018 3:09:42 PM
It is intended that shoulder paving, rumble strips and rumble stripes will be placed at all feasible locations . In locations where field conditions, existing guardrail, or other obstructions do not make it feasible to install the aforementioned, the Engineer may eliminate the work item. Guardrail removal and reinstallation is not included in this proposal.
Displaying questions 1 - 1 (of 1)
Page: