Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
N20
112287
(NFO)9999-967-430,N501
5/18/2018
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Unanswered questions
Type:
Other
Question
Date:
5/21/2018 11:34:11 AM
There are some questions that have not been answered. Will they be answered today?
Answer
Date:
Subject:
Contract Value
Type:
Proposal
Question
Date:
5/16/2018 4:47:20 PM
Will VDOT be required to give the contractor task orders that equal to 70% of the contract value?
Answer
Date:
5/17/2018 8:06:21 AM
Yes, that is the intent in accordance with Section 104.01 of the proposal.
Subject:
Task Orders
Type:
Proposal
Question
Date:
5/16/2018 4:46:11 PM
How many task orders will the contractor be expected to work on at one time? Some contracts have required that the contractor have enough manpower to work on 4 task at a time.
Answer
Date:
5/22/2018 8:17:03 AM
Task orders will be issued as they are ready to go and fixed completion dates will be agreed upon per task order. There may be task orders issued with staggered schedules and completion dates. The expectation is that the contractor can move from 1 task order to the next with minimal delay.
Subject:
Material on Hand
Type:
Proposal
Question
Date:
5/16/2018 4:44:20 PM
According to the proposal page 4 section 106.08 the contractor is required to keep material on hand but will not receive payment for this material unless it is installed. However, the material that will be bought back at the end of the contract does not come close to equal of what is required to keep on hand. It is our understanding that this was supposed to be evaluated in order to keep the pricing low. How is the contractor supposed to take this potential loss on the contract or can payment for stored material be added this contract?
Answer
Date:
5/22/2018 8:18:19 AM
The intent is to either use up all material on hand in identified task orders in the last 6 months and/or reimburse the contractor for whatever is left of the stored material on hand that’s in good condition. We will pay for stored materials on hand after the task orders, but all material paid for this way must be delivered to us in good condition.
Subject:
PA-4 Pedestrian Pole
Type:
Specifications
Question
Date:
5/16/2018 4:40:40 PM
According to the revision for the Accessible Pushbutton Station PA-4 the 6' PA-4 pole is supposed to be paid for as a separate line item. Should there be a line item added to this contract?
Answer
Date:
5/22/2018 8:22:59 AM
The Ped Buttons can be mounted on other pole types; locations that may require the PA-4 pole type, work orders may be issued.
Question
Date:
5/16/2018 4:40:39 PM
According to the revision for the Accessible Pushbutton Station PA-4 the 6' PA-4 pole is supposed to be paid for as a separate line item. Should there be a line item added to this contract?
Answer
Date:
5/22/2018 10:17:01 AM
The Ped Buttons can be mounted on other pole types; locations that may require the PA-4 pole type, work orders may be issued.
Subject:
1510 Video Detection Type I
Type:
Proposal
Question
Date:
5/8/2018 3:52:43 PM
Bid item says specifications is attached. Could not locate in proposal.
Answer
Date:
5/10/2018 3:10:45 PM
The will be addressed in the revision forthcoming.
Subject:
1430 UPS Cabinet
Type:
Proposal
Question
Date:
5/8/2018 3:52:22 PM
Bid item says specifications is attached. Could not locate in proposal.
Answer
1 previous answer(s)
Date:
5/10/2018 3:24:32 PM
This will be addressed in the revision forthcoming.
Subject:
1290 Master Controller Type I
Type:
Proposal
Question
Date:
5/8/2018 3:52:05 PM
Bid item says specifications is attached. Could not locate in proposal.
Answer
1 previous answer(s)
Date:
5/10/2018 3:25:22 PM
This will be addressed in the revision forthcoming.
Subject:
Controller Type II
Type:
Proposal
Question
Date:
5/8/2018 3:51:13 PM
Bid item says specifications is attached. Could not locate in proposal.
Answer
Date:
Question
Date:
5/8/2018 3:51:12 PM
Bid item says specifications is attached. Could not locate in proposal.
Answer
Date:
Question
Date:
5/8/2018 3:51:11 PM
Bid item says specifications is attached. Could not locate in proposal.
Answer
1 previous answer(s)
Date:
5/10/2018 3:25:29 PM
This will be addressed in the revision forthcoming.
Subject:
1110 Controller Type I
Type:
Proposal
Question
Date:
5/8/2018 3:50:52 PM
Bid item says specifications is attached. Could not locate in proposal.
Answer
1 previous answer(s)
Date:
5/10/2018 3:25:35 PM
This will be addressed in the revision forthcoming.
Displaying questions 1 - 10 (of 16)
Page:
1
2
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/26/2024 10:06:21 PM
2008