Project Info
Order Number UPC State Project Number Last Date to Post Questions
N35 107769 (NFO)0095-964-S55, N501 5/18/2018
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Sign Lighting Type: Proposal
Question Date: 5/18/2018 11:17:08 AM
The proposal shows installing 25ea Luminaire Retrieval systems being installed on overhead sign structures. However there are no details how the lighting systems get connected to the existing lighting circuits. Will these systems be connected at a later date by the department or under a separate contract?  
Answer   Date: 5/22/2018 11:02:43 AM
Connections between the luminaire retrieval systems and any existing circuits will be done as part of this contract. Per Section 700 of the 2018 Supplement to the 2016 Virginia Department of Transportation Road and Bridge Specifications, electrical systems are included with a new overhead sign structure. The Contractor shall coordinate with VDOT, as per General Note 16 of the No-Plan Assembly, prior to removal of any existing electrical items. This coordination will include the connection of new systems to existing lighting circuits.  
 
Subject: Location 5-7 Type: Plan
Question Date: 4/16/2018 1:32:27 PM
Since there is a significant elevation drop at this location and as far as we can tell nowhere to put the sign. Can this sign location be eliminated and possible add the verbage or sign to location 1-9 and 1-10?  
Answer   Date: 5/8/2018 8:14:06 AM
No, the sign location cannot be eliminated. The determination of foundation quantities considers the elevation drop and should be bid accordingly.  
 
Subject: Location 1-9 Type: Plan
Question Date: 4/16/2018 1:30:45 PM
Since there is a significant elevation drop at this location, can this be relocated closer to the existing cantilever?  
Answer   Date: 5/8/2018 8:13:43 AM
No, the sign structure cannot be relocated closer to the existing cantilever. The determination of foundation quantities considers the elevation drop and should be bid accordingly.  
 
Subject: Lane Closures Type: Proposal
Question Date: 4/16/2018 1:29:41 PM
Please clarify who will be responsible for entering the lane closure information in LCAMS. Page 82 Section 3 Subsection 1 states that the contractor is responsible and page 125 section 1 a& b states that VDOT is responsible.  
Answer   Date: 4/17/2018 7:51:00 AM
The contractor is responsible for entering the lane closure information in LCAMS as assigned in the Special Provision for Lane Closure Coordination (LCC)/Lane Closure Implementation (LCI) which begins on Page 82 of the proposal. The No-Plan Assembly will be modified to remove the conflict.  
 
Subject: Overhead Sign Structures Type: Other
Question Date: 4/16/2018 1:27:29 PM
Will VDOT allow extruded sign panel on overhead structures also?  
Answer   Date: 4/17/2018 7:50:02 AM
Extruded sign panels are not allowed to be used on the projects overhead structures. Extruded Sign Panels will only be permitted on ground mounted signs, as approved.  
 
Subject: Haul Permits Type: Permits
Question Date: 4/4/2018 8:54:02 AM
Will the Contractor be required to obtain Haul permits if the need arises to transport structures from a stock yard to its designated site? Or will the State Police assist and permits not be required?  
Answer   Date: 4/9/2018 4:09:08 PM
The DMV establishes the requirements for when a hauling permit is required. The contractor shall be responsible for obtaining the hauling permit if it is required. The contractor should not expect assistance from State Police when transporting structures from a stock yard to its designated site.  
 
Subject: OH Sign Structure Foundations Pay Item Type: Proposal
Question Date: 4/4/2018 8:50:08 AM
Pages 92-115 of the Contract Provisions references various procedures & requirements for drilled shafts, excavation, CSL testing, etc. Each designated item, according to the contract, is measured and paid per EA or LF. However there is nothing in the contract covering these items of work. Are drilled shafts required for this project? The 2016 Specifications provide the contractor with options of spread footings, drilled pier caps, or driven piles. What is the type of foundation the Department is requiring under Item 50575 OH Sign Structure Foundation?  
Answer   Date: 4/16/2018 8:08:00 AM
Drilled shafts are not being required. The Special Provision (Pages 92 - 115) will be removed from the proposal.  
 
Subject: Luminaire Retrieval System Type: Other
Question Date: 4/3/2018 11:56:30 AM
Line Item # 0540 Lighting Sign Luminaire Retrieval System 584 LF. This footage is the amount of signage lengths going on the structure. This suggest that each sign will have its own lights and Not a Retrieval System. If a Retrieval System is required it will need to run to the shoulder of the road and I am estimating the linear feet should be around 900 LF. Please confirm if a Retrieval System is needed?  
Answer   Date: 4/16/2018 8:07:07 AM
The Lighting Sign Luminaire Retrieval System is required. The Item Quantity will be increased in the Schedule of Items.  
 
Subject: Existing Structure # 1-13 Type: Other
Question Date: 4/3/2018 11:36:51 AM
On sheet 160 of the proposal book (Location # 1-13 Existing Span Structure) they are taking a sign off and putting a new sign on an existing structure. It appears to me that the new sign is bigger than the one they are taking off. In the Notes on sheet 160 of the proposal book it states “The Structure Shall Be Designed”. Is there any design work required for this structure? If Designing of Existing Structure is needed, How are we to prove an Old Design with the New VDOT Standards and Specs?  
Answer   Date: 4/16/2018 8:02:53 AM
The plan note on Sheet 160 will be revised and the proposal will not require this existing structure to be designed.  
 
Subject: Sign Post Sizes Type: Other
Question Date: 4/3/2018 11:34:28 AM
Location No. 5-4 (Type VIA-W) W14x26 Post, Location No. 5-6 (Type VIA-S) W12x16 Post, Location No. 5-7 (Type VIA-C) W10x12Post, & Location No. 5-8 (Type VIA-T) W12x19 Post Sizes doesn’t match the Bid Item Sizes (Item # 0130 W12x16) (Item # 0140 W14x22) (Item # 0150 W16x26)? Which should we be quoting?  
Answer   Date: 4/16/2018 8:07:38 AM
Line Item #'s 140 and 150 will be removed from the Schedule of Items and Item #'s 50410, 50413, and 50415 will be added to the Schedule of Items.  
 

Displaying questions 1 - 10 (of 16)
Page: 1 2 First Previous Next Last