    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: SMA Work Dates Type: Proposal
Question Date: 2/20/2018 8:27:50 AM
Since the Salem District Plant Mix Proposals include a larger quantity of SMA this season than normal, would the Department consider extending the SMA work date until November 1, 2018 for this project?  
Answer   1 previous answer(s) Date: 2/26/2018 2:45:42 PM
No, this work needs to be completed as specified.  
 
Subject: Multiple Lane Closures Allowable Work Hours Type: Proposal
Question Date: 2/19/2018 11:11:53 AM
Will the Work Hours ( Sunday thru Friday from 10:00 pm unitl 6:00 am ) be allowed for a multiple lane closure ( example: Closing Lane 1 and Lane 2 at the same time to allow for work to be performed safely In Lane 2 ) ?  
Answer   Date: 3/14/2018 1:13:32 PM
Yes, the contractor can close two lanes in the three-lane section between 10pm – 6am. The contractor shall follow TTC 18.1 VDOT will also remove the SMA time restrictions and add the SP for early completion incentives via addendum.  
 
Subject: Incorrect Proposal on Falcon Type: Proposal
Question Date: 1/15/2018 10:54:24 AM
When you access this project on Falcon, a surface treatment project for Giles-Montgomery-Pulaski form 2016 with the same Order No. is what you receive  
Answer   Date: 1/16/2018 8:02:26 AM
Falcon has been updated with the correct Proposal.  
 

Displaying questions 1 - 3 (of 3)