Advertisements   Division Home   Bid Results   Bid Tabs   Ad Report   VDOT Forms
Project Info
Order Number UPC State Project Number Last Date to Post Questions
618 110814 PM6C-966-F18,P401 1/19/2018
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Mix types Type: Proposal
Question Date: 1/16/2018 10:22:45 AM
On certain sections of Rt. 17 in Gloucester Cty. the proposal shows SMA for mainline and SM12.5A for shoulders. However, some of these shoulders are not full paving widths.Is it the Departments intention to use SMA for these less than full width shoulders??  
Answer   Date: 1/18/2018 1:34:20 PM
The proposal is correct. It is the Department’s intention to place SMA only on the mainline and SM-12.5A on all other areas, shoulders, turn lanes, crossovers, connections etc.  
 
Subject: Letting Date Type: Proposal
Question Date: 12/6/2017 3:07:23 PM
Will the 600 series Orders be delayed as per the announcement?  
Answer   Date: 12/7/2017 3:28:59 PM
yes  
 

Displaying questions 1 - 2 (of 2)
Page: 1 First Previous Next Last