Question List
Subject: Surface Prep Type II Type: Specifications
Question Date: 1/16/2018 11:46:11 AM
Will all of the Surface Prep Type II be performed prior to the Flexible Pavement Planing?  
Answer   Date: 1/23/2018 4:33:58 PM
Yes, all of the Surface Prep Type II (patching) should be performed prior to the Flexible Pavement Planing.  
 
Subject: Performance Grade Liquid Asphalt for BM-25.0D HMHB Type: Proposal
Question Date: 1/16/2018 11:31:52 AM
What PG liquid asphalt will be used for the BM-25.0D (HMHB +0.4)? The detail sheets specify PG 76-22 and the detail on page 186 notes PG 70-22.  
Answer   Date: 1/18/2018 1:45:03 PM
Please follow Table 3 Recommended Performance Grade of Asphalt of SP315-000160-00 ‘VDOT Special Provision for BM-25.0D with increased asphalt content. This spec was part of the latest revision.  
 
Subject: Pavement Fabric Type: Specifications
Question Date: 1/15/2018 9:45:30 AM
Is there data available to show locations of existing joint fabric that may be encountered during milling operations? If those locations have fabric that span multiple lanes, the milling machine could pull the entire length of fabric and compromise the pavement in the adjacent lanes. How would Vdot compensate for this contingency?  
Answer   Date: 1/18/2018 11:01:24 AM
Joint fabrics could be encountered along transverse joints on I-495 express lanes. Locations will be marked prior to construction and the contractor will be required to saw-cut prior to milling operation.  
 
Question Date: 1/19/2018 11:15:42 AM
Will the saw cutting be paid for under line items 20 or 30 when they are clarified?  
Answer   Date: 1/19/2018 3:09:02 PM
Both saw cutting are same item. By typo, the I-495 SB and I-495 NB saw cutting showed up as separate items in the summary. Please consider this as one item with total of 15,996 LF.  
 
Subject: Surface Prep. Ty. II Type: Specifications
Question Date: 1/15/2018 9:30:07 AM
What are the intended dimensions on each side of the transverse joints in the Ty. II patching?  
Answer   Date: 1/18/2018 11:29:14 AM
All Type II patching will be 4 inches deep or up to the top of concrete. Type II patching estimated at 2 inches in the contract will be converted to Type II patching 4 inches deep. Locations will be marked prior to construction.  
 
Subject: Saw-cut Asph. Conc. Type: Proposal
Question Date: 1/11/2018 2:11:35 PM
Can you provide a clarification on the difference in line item 20 and 30, saw and seal concrete joint.?  
Answer   Date:
 
 
Subject: Asphalt Price Adjustment Type: Specifications
Question Date: 1/5/2018 8:49:14 AM
Will there be a price adjustment for the asphalt material for the SM-12.5E High Polymer and the BM 25.0D (HMHB+0.4) PG76-22? These mixes are not shown on the Master Listing on pages 81 - 83. If so, will it be based on PG 64S-22 as specified on page 80?  
Answer   Date: 1/9/2018 9:40:44 AM
They will be adjusted according to 64-22S.  
 
Question Date: 1/5/2018 9:21:11 AM
Can a specification be provided for the BM 25.0D HMHB+0.4 mix. There isn't one in the proposal book or the 2017 spec book? Also, is there a limit to the RAP for this mix?  
Answer   Date: 1/5/2018 1:59:31 PM
This will be issued as an addendum next week.  
 
Subject: Letting date. Type: Proposal
Question Date: 12/5/2017 3:25:14 PM
Will Order 948 be delayed as per the announcement?  
Answer   Date: 12/7/2017 3:39:08 PM
Yes  
 
Subject: Surface Prep and Restoration Type: Other
Question Date: 11/16/2017 1:12:25 PM
Will all patching be a minimum of 6' to 7' wide?  
Answer   Date: 11/20/2017 10:48:09 AM
In most cases, the minimum patching width is 6’. However, there are some locations where the patching width is specified differently in the contract. Therefore, if the patching width is not specified otherwise in the contract, then the minimum width is 6’.  
 

Displaying questions 1 - 8 (of 8)