Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
M23
86726
(NFO)0649-025-713, M501
8/18/2017
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Type:
Plan
Question
Date:
8/18/2017 11:52:17 AM
Why is directional boring set up for a 2"water service line to two houses?
Answer
Date:
8/21/2017 4:24:30 PM
The depth of installation of the proposed 2” water line as shown on sheet 5(3) and profile sheet 5(3B) the directional drilling has been identified as required. Access to residents and others must be maintained and remain open at all times during construction.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/29/2024 8:22:22 AM
2008