Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
L81
108416
(NFO)0058-087-664,N501,B640
4/21/2017
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Traffic control
Type:
Proposal
Question
Date:
4/20/2017 2:27:45 PM
There are two bid items in the proposal for maintenance of traffic that are lump sum bid items. Can we leave the temporary lane closure up from Monday to noon on Friday without putting down temporary line marking tape. We will be working continuously during that time. All lanes will be open from noon Friday to Monday.
Answer
Date:
4/21/2017 4:15:26 PM
The Contractor does not need to use temporary line marking tape with the drums as long as they are not encroaching into the other travel lane.
Question
Date:
4/10/2017 4:30:10 PM
On page 129 under allowable closure hours the contractor is allowed to do a 24hr closure Monday Through Thursday. Three items below the chart it states that all lanes shall be open to traffic at the end of each workday. Which is correct? Considering that the contract is doing joint closures it makes sense that the 24hr 4 days a week should prevail?
Answer
Date:
4/11/2017 3:05:25 PM
The contractor may work for 24 hours Monday through Thursday. The statement that all lanes shall be open to traffic at the end of each work day pertains to the contractor needing to remove ALL Work Zone equipment to safely allow all lanes to be open when they are not working.
Subject:
As Builts
Type:
Plan
Question
Date:
4/10/2017 4:20:15 PM
Can the as builts be made available?
Answer
Date:
4/14/2017 4:06:25 PM
Posted at http://www.virginiadot.org/business/const/default.asp (Under Announcements)
Subject:
BIDITEMS
Type:
Proposal
Question
Date:
3/27/2017 10:48:54 AM
The proposal includes through Biditem 180, but the BidX files only include through Biditem 150. Please advise.
Answer
Date:
3/30/2017 1:27:12 PM
BidX is correct. VDOT will issue an addendum.
Displaying questions 1 - 3 (of 3)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/17/2024 11:00:47 PM
2008