Subject: 14" CFRP Prestressed Concrete Pile Type: Specifications
Question Date: 4/25/2017 12:32:18 PM
We have recently learned the carbon fiber prestressing strands and spiral have a minimum 4 month lead time after approved shop drawings to reach the precast pile manufacturer. With this lead time, we will be unable to meet the November 17, 2017 completion date as specified. Please clarify.  
Answer   Date:
 
 
Subject: Concrete Coating Type: Specifications
Question Date: 4/20/2017 11:17:36 AM
Will the abutment backwall / wingwall fascias require protective coating from +5.0 to -5.0 as outlined in Specification Section 404.03 (i) Concrete Exposed to Tidal Water ?  
Answer   Date: 4/21/2017 4:13:27 PM
Yes, the abutment backwall/wingwall fascias shall be coated in accordance with Specification 404.03(i) from elev. +5.0 to -5.0. As stated in Specification 404.08, the protective coating is incidental to the cost of the concrete.  
 
Subject: 14" Prestr. Concrete Pile Type: Plan
Question Date: 4/20/2017 11:03:03 AM
Plan Sheet 5 of 17, is there a pile on the back row @ the construction centerline ? The plan does not indicate one. If there is not one , the quantity needs revising.  
Answer   Date: 4/21/2017 3:56:41 PM
There is not a pile on the back row at the construction baseline. The prestressed concrete pile quantity is in accordance with 10 plumb piles and 13 battered piles minus the quantity for 1 test pile per abutment. The Driving Test quantity is for one battered pile with some extra length included.  
 
Subject: Directionall Drilled Waterline Qualifications Type: Specifications
Question Date: 4/12/2017 12:22:01 PM
There is a special provision for this work which requires Contractor Qualifications. Will this work be considered a specialty item that does not require VDOT pre-qualifications to bid the project? Since this work must be done first, there may not be enough time to get a contractor pre-qualified and still meet the project completion date  
Answer   Date: 4/18/2017 11:20:04 AM
The qualifications which I assume your are referencing to has to do with Horizontally Directional Drilling of Waterlines. This should be something that a VDOT prequalified utility contractor can do. If there are no prequalified vendors for this work, the District can declare it a specialty.  
 
Subject: Permits Type: Permits
Question Date: 3/28/2017 2:43:14 PM
COE Section 404 Permit expired on 3/18/17. Will this permit be renewed before construction?  
Answer   Date: 3/28/2017 3:56:51 PM
YES  
 
Subject: Battered Pile Type: Plan
Question Date: 3/28/2017 2:40:35 PM
Sheet 4 of 17 indicated battered pile at a 4:12 Sheet 5 of 17 indicated battered pile at a 3:12 What is the correct batter?  
Answer   Date: 3/30/2017 11:48:59 AM
The correct pile batter is 3:12 .  
 

Displaying questions 1 - 6 (of 6)