Project Info
Order Number UPC State Project Number Last Date to Post Questions
L68 105110 (NFO)0106-074-765, C501 4/21/2017
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: PF-8 Standards Type: Plan
Question Date: 3/16/2017 3:39:32 PM
Does the PF-8 (Signal Pole Foundation) require a 1' reveal? Sheet 6(1A)1 is an older version and only requires a 3" reveal.  
Answer   Date: 3/21/2017 2:40:08 PM
The state will be furnishing the traffic poles for this project. The poles meet the 2007 standards for traffic signal poles & arms foundations. Therefore Sheet 6(1A)1 should be followed.  
 
Subject: Fixed Completion Date Type: Proposal
Question Date: 3/16/2017 3:30:43 PM
The fixed completion date shown in the proposal is November 16, 2017. However, the Interim Completion Date on Page 5 is December 14, 2017 with a 20 Calendar day incentive. Please verify that these dates are accurate.  
Answer   Date: 3/21/2017 3:19:19 PM
The new FCD is 12/22/17 & the Interim Completion Date is 11/16/2017. An addendum will be issued.  
 

Displaying questions 1 - 2 (of 2)