Order Number
UPC
State Project Number
Last Date to Post Questions
L68
105110
(NFO)0106-074-765, C501
4/21/2017
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
PF-8 Standards
Type:
Plan
Question
Date:
3/16/2017 3:39:32 PM
Does the PF-8 (Signal Pole Foundation) require a 1' reveal? Sheet 6(1A)1 is an older version and only requires a 3" reveal.
Answer
Date:
3/21/2017 2:40:08 PM
The state will be furnishing the traffic poles for this project. The poles meet the 2007 standards for traffic signal poles & arms foundations. Therefore Sheet 6(1A)1 should be followed.
Subject:
Fixed Completion Date
Type:
Proposal
Question
Date:
3/16/2017 3:30:43 PM
The fixed completion date shown in the proposal is November 16, 2017. However, the Interim Completion Date on Page 5 is December 14, 2017 with a 20 Calendar day incentive. Please verify that these dates are accurate.
Answer
Date:
3/21/2017 3:19:19 PM
The new FCD is 12/22/17 & the Interim Completion Date is 11/16/2017. An addendum will be issued.
Displaying questions 1 - 2 (of 2)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/24/2024 11:48:20 PM
2008