Subject: Mobilization Type: Proposal
Question Date: 2/9/2017 2:33:34 PM
We feel that due to this Project being located in two areas that a "Mobilization" bid item should be added to account for establishing a work area in separate areas  
Answer   Date: 2/13/2017 2:52:44 PM
Mobilization cost are to be included in the bid price for other items.  
 
Subject: DBE Folder Type: Other
Question Date: 2/4/2017 10:52:04 AM
The expedite file from Bid Express does not have a DBE folder. Also, the printed proposal mailed to us does not have a DBE percentage shown on form C-111, the field is blank.  
Answer   Date: 2/9/2017 3:21:35 PM
An addendum is being issued today.  
 
Subject: Date Restriction for Work Type: Proposal
Question Date: 1/31/2017 1:47:01 PM
Considering the completion date for this project, why is the Full Depth Patching in Pulaski Co. restricted to dates in April & May? Could dates during June & July be used as allowed for the Montgomery Co. location?  
Answer   Date: 2/2/2017 4:20:07 PM
1.) Longer duration delays to motorists are expected in Pulaski County than Montgomery, due to the lack of a good alternate route and the presence of an uphill grade. ~~~ 2.0 No. Traffic counts are historically higher in the months of June and July, and the Department is not willing to accept the potential motorist delays, caused by an extended closure during these months, in Pulaski County.  
 
Subject: Limitation of Operations Type: Proposal
Question Date: 1/31/2017 10:40:12 AM
The SPCN for Full Depth Patching limits the extended closure to one per work location, when would the patching be completed if the contractor could not complete all patch areas during the time allowed due to weather or unforeseen circumstances and opened the area to traffic on time to prevent user fee assessment? Why is there a limit of one time for the extended closure?  
Answer   Date: 2/2/2017 4:20:42 PM
If the full depth patching is not completed during one of the allowable extended closures, it may be completed from Sunday to Thursday, between 9:00 PM and 6:00 AM daily. Due to the expected delays for motorists resulting from an extended length closure, the Department is only willing to allow one per location.  
 
Subject: Proposal is not Available of Falcon Type: Proposal
Question Date: 1/23/2017 9:37:23 AM
When will this proposal be available on the Falcon website?  
Answer   Date: 1/23/2017 1:13:00 PM
Available now.  
 