Question List
Subject: Traffic Groupings Type: Proposal
Question Date: 1/17/2017 10:03:12 AM
Does the Department intend to revise the incorrect traffic groupings prior to January 25th?  
Answer   Date: 1/17/2017 4:41:07 PM
Will be posted by tomorrow.  
 
Subject: Traffic Groups Type: Plan
Question Date: 12/13/2016 9:26:18 AM
The route details list all routes (except Route 606) as Traffic Group I, this seems low on several routes, specifically Rt. 1072 Randolph Dr, Rt 1872 Marshfield Dr & Rt 1880 Crossroads Dr. Can you please verify the traffic groups?  
Answer   Date:
 
 
Question Date: 12/13/2016 10:31:47 AM
Also may want to double check Routes 1792 Bartholomew Fair Dr & Rt 1793 Nokes Blvd  
Answer   Date:
 
 
Subject: Provision (C515C00) - Predictable Weather Type: Other
Question Date: 12/2/2016 2:28:58 PM
Provision (C515C00) – (c515c00-0916) Section III.A.1 states” or is prevented from doing so by predictable weather”. Please define what predictable weather is and the service that should be used for that purpose.  
Answer   Date: 12/13/2016 3:52:41 PM
“Predictable weather” is defined as that weather being forecasted by a reputable source at the time a decision to proceed with the Work is being made. Any reputable weather service may be used for this determination, and this may be a point of discussion and agreement at the Pre-Construction Meeting.  
 
Subject: Provision (C515C00) Type: Other
Question Date: 12/2/2016 2:28:18 PM
Provisions (C515C00) – (c515c00-0916) Section III.A.1 states “The Contractor will be limited in the case of regular pavement planing, whether in a single lane or multiple lane operation, to only that amount of pavement that can be paved back to its final elevation within 24 hours of completion of planing that roadway or portion of roadway.” Section III.A.1. states “Performance pavement planing may be performed in multiple lanes across the entire widths of the lanes up 4 miles of travel lane unless otherwise stated in the Contract. Performance planed travel lane surfaces must be paved back to their final elevation within 96 hours from the end of the performance planing operation.” We request that VDOT remove these restrictions on roadways in which multiple operations will take place to repair the underlying pavements such as planning 2”-4” and placing IM-19.0 in that area, or areas in which surface preparation & restoration is to take place after pavement planning has taken place, or any other areas in which subsurface activities will take place.  
Answer   Date: 12/9/2016 2:58:59 PM
This spec has been revised and an addendum will be posted later today.  
 
Subject: Provision (C315H00) Type: Other
Question Date: 12/2/2016 2:16:32 PM
Provisions (C315H00) - (c315h00-0916) Section 315.05(c) states “the longitudinal joint shall be uniform in appearance, shall not vary from a straight line more than 1 inch in 50 feet for a maximum distance of 500 feet on tangent alignment, and shall be on a true arc on curved alignment.” We request VDOT remove this provision since it is not achievable.  
Answer   Date: 12/9/2016 2:58:40 PM
This spec has been revised and an addendum will be posted later today.  
 

Displaying questions 1 - 5 (of 5)