Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
K31
107120
(NFO)0658-097-S94,N501
8/19/2016
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
shoulder stone
Type:
Bid Sheet
Question
Date:
8/23/2016 11:40:01 AM
Will the 40K TN of stone really be used? In past years the actual quantity has been much less.
Answer
Date:
Subject:
21B Quantity
Type:
Proposal
Question
Date:
8/16/2016 8:39:52 AM
On the previous 4 to 5 paved shoulder projects let in the Bristol District, the actual quantity of mineral aggregate 21B's required to construct the project appears to be is less 10% of the quantity included in the proposals/contract. The proposal for K31 includes 42,000+ Tons of 21Bs. Based on the history of the previous projects, how many tons will the Department actually require the contractor to install for K31?
Answer
Date:
8/16/2016 11:39:36 AM
On this project in the area of the Coeburn bypass ( MP 46.5 to MP 49.9 )you will have 14’ to 10’ Shoulders. That is the reason for a large amount of aggregate 21B's.
Subject:
Typical Section
Type:
Proposal
Question
Date:
8/9/2016 8:52:49 AM
Is it possible to get a typical section for this project to show depths of stone, and asphalt items?
Answer
Date:
8/9/2016 10:55:13 AM
This will be posted on the Construction website under ANNOUNCEMENTS.
Displaying questions 1 - 3 (of 3)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/29/2024 5:47:44 AM
2008