Subject: Traffic Control Type: Specifications
Question Date: 5/18/2016 12:00:39 PM
What are the allowable lane closure or flagging operation hours for each structure?  
Answer   Date: 5/19/2016 9:10:41 AM
Please see the Temporary Traffic Control Plan, pages 153-156.  
 
Subject: As Built Plans Type: Plan
Question Date: 5/11/2016 10:58:45 AM
This seems to always happen with the plan portion of the project. I see that the plans are available, however when I click to view it gives me a blank screen. Please advise.  
Answer   Date: 5/11/2016 1:18:24 PM
You should be able to see them now.  
 
Question Date: 5/12/2016 4:29:05 PM
Zip file does not work.  
Answer   Date:
 
 
Subject: Traffic Control Type: Plan
Question Date: 5/10/2016 4:31:42 PM
Are flagging operations allowed on Rte 218 over RF& P RR?  
Answer   Date: 5/12/2016 2:27:44 PM
A temporary traffic signal on the Rt. 218 bridge RF&P Railroad (Abandoned) is required in accordance with page 156 of the proposal.  
 
Subject: Traffic Control Type: Plan
Question Date: 5/10/2016 4:30:00 PM
Is a traffic signal still required with the current space on the shoulders before the bridge at 200 over Carters Creek  
Answer   Date: 5/12/2016 2:28:10 PM
A temporary traffic signal on the Rt. 200 bridge over Carter’s Creek is required in accordance with page 155 of the proposal. The temporary traffic signal shall be designed to operate within the existing geometric conditions along the roadway.  
 
Subject: Traffic Contral Type: Plan
Question Date: 5/10/2016 4:29:06 PM
On Structure 1945, please verify that blasting and painting operations are allowed from the bridge deck?  
Answer   Date: 5/12/2016 12:03:04 PM
Blasting and painting operations are allowable from the bridge deck as long as applied loads from construction vehicles and equipment does not exceed the structure’s capacity. Any construction vehicle and equipment staged from the deck shall be analyzed and submitted to the Department for review to ensure the loading does not exceed the structure’s capacity. Operations from the bridge deck requiring a lane closure shall only be allowed during the hours specified on page 154 of the proposal.  
 