Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
J90
101376
(NFO) 0058-038-729,C501,B618
6/17/2016
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Revisions
Type:
Plan
Question
Date:
6/7/2016 3:14:28 PM
We don't see Sheet 2H(1) and 2H(2) on Falcon?
Answer
Date:
6/10/2016 11:52:08 AM
They are there now.
Subject:
Structural Steel
Type:
Proposal
Question
Date:
5/19/2016 9:54:12 PM
We are hearing from fabricators that plate girder of this size are late 1 st quarter 2017 (and possibly early 2nd quarter 2017) deliveries. This will make the September completion date of the phased construction bridge extremely difficult. Given the fabricator's estimated delivery schedule, can consideration be made to extending the completion date into mid fourth quarter 2017?
Answer
Date:
Subject:
Attenuators
Type:
Plan
Question
Date:
5/18/2016 2:26:02 PM
The special design impact attenuator 2H(1) and the Re-directive portable impact attenuator 2H(2) are not showing up in the plan sheets.
Answer
Date:
Subject:
Bid Item 0210 Flexible Pavement Planing 0" - 2"
Type:
Bid Sheet
Question
Date:
5/17/2016 4:57:57 PM
Please confirm the bid quantity of 21,280 sy
Answer
Date:
5/19/2016 8:44:45 AM
The quantity of 21,280 is actually S.F., and should have been divided by 9 to give us the correct S.Y. quantity of 2,365. A revision will be posted.
Subject:
Subsurface
Type:
Proposal
Question
Date:
5/15/2016 8:09:23 PM
Please post any available soils reports or borings
Answer
Date:
5/17/2016 9:24:22 AM
Geotechnical report has been posted to Falcon.
Subject:
Bridge Plans
Type:
Plan
Question
Date:
5/15/2016 8:08:44 PM
Please post any available existing bridge plans.
Answer
Date:
5/17/2016 7:28:42 AM
Existing bridge plans have been posted to Falcon.
Subject:
Pre-bore Pilings
Type:
Bid Sheet
Question
Date:
4/22/2016 8:08:17 AM
The pay item for the temporary casing of the pre-bore pilings has been left out of the bid items. Please clarify.
Answer
Date:
4/22/2016 1:40:44 PM
All costs for stabilization of the entire pre-boring piles operation (equipment, excavation, temporary casing, fluids, etc.) shall be incidental to the pre-boring of the piles.
Subject:
Roadway Baselines
Type:
Plan
Question
Date:
4/22/2016 8:05:17 AM
On plan sheet 1G (Construction Alignment Data), why are there two distinct baseline chains shown for Route 58, and why doesn't the alignment of the construction baseline on plan sheets 3, 4, and 5 match the alignment of the baseline on plan sheets 3RW, 4RW, and 5RW?
Answer
Date:
4/22/2016 1:43:36 PM
The data shown on plan sheet 1G, labeled “RTE. 58 – CONSTRUCTION,” pertains to the construction baseline shown on plan sheets 3, 4, and 5. The data shown on plan sheet 1G, labeled “RTE. 58 – RIGHT OF WAY ONLY,” pertains to the baseline shown on plan sheets 3RW, 4RW, and 5RW. The baseline labeled “RTE. 58 – CONSTRUCTION” was developed after right of way had been acquired, in order to comply with VDOT’s policy titled “Practical Design Flexibility in the Project Development Process,”.
Displaying questions 1 - 8 (of 8)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/29/2024 9:02:25 AM
2008