Project Info
Order Number UPC State Project Number Last Date to Post Questions
J90 101376 (NFO) 0058-038-729,C501,B618 6/17/2016
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Revisions Type: Plan
Question Date: 6/7/2016 3:14:28 PM
We don't see Sheet 2H(1) and 2H(2) on Falcon?  
Answer   Date: 6/10/2016 11:52:08 AM
They are there now.  
 
Subject: Structural Steel Type: Proposal
Question Date: 5/19/2016 9:54:12 PM
We are hearing from fabricators that plate girder of this size are late 1 st quarter 2017 (and possibly early 2nd quarter 2017) deliveries. This will make the September completion date of the phased construction bridge extremely difficult. Given the fabricator's estimated delivery schedule, can consideration be made to extending the completion date into mid fourth quarter 2017?  
Answer   Date:
 
 
Subject: Attenuators Type: Plan
Question Date: 5/18/2016 2:26:02 PM
The special design impact attenuator 2H(1) and the Re-directive portable impact attenuator 2H(2) are not showing up in the plan sheets.  
Answer   Date:
 
 
Subject: Bid Item 0210 Flexible Pavement Planing 0" - 2" Type: Bid Sheet
Question Date: 5/17/2016 4:57:57 PM
Please confirm the bid quantity of 21,280 sy  
Answer   Date: 5/19/2016 8:44:45 AM
The quantity of 21,280 is actually S.F., and should have been divided by 9 to give us the correct S.Y. quantity of 2,365. A revision will be posted.  
 
Subject: Subsurface Type: Proposal
Question Date: 5/15/2016 8:09:23 PM
Please post any available soils reports or borings  
Answer   Date: 5/17/2016 9:24:22 AM
Geotechnical report has been posted to Falcon.  
 
Subject: Bridge Plans Type: Plan
Question Date: 5/15/2016 8:08:44 PM
Please post any available existing bridge plans.  
Answer   Date: 5/17/2016 7:28:42 AM
Existing bridge plans have been posted to Falcon.  
 
Subject: Pre-bore Pilings Type: Bid Sheet
Question Date: 4/22/2016 8:08:17 AM
The pay item for the temporary casing of the pre-bore pilings has been left out of the bid items. Please clarify.  
Answer   Date: 4/22/2016 1:40:44 PM
All costs for stabilization of the entire pre-boring piles operation (equipment, excavation, temporary casing, fluids, etc.) shall be incidental to the pre-boring of the piles.  
 
Subject: Roadway Baselines Type: Plan
Question Date: 4/22/2016 8:05:17 AM
On plan sheet 1G (Construction Alignment Data), why are there two distinct baseline chains shown for Route 58, and why doesn't the alignment of the construction baseline on plan sheets 3, 4, and 5 match the alignment of the baseline on plan sheets 3RW, 4RW, and 5RW?  
Answer   Date: 4/22/2016 1:43:36 PM
The data shown on plan sheet 1G, labeled “RTE. 58 – CONSTRUCTION,” pertains to the construction baseline shown on plan sheets 3, 4, and 5. The data shown on plan sheet 1G, labeled “RTE. 58 – RIGHT OF WAY ONLY,” pertains to the baseline shown on plan sheets 3RW, 4RW, and 5RW. The baseline labeled “RTE. 58 – CONSTRUCTION” was developed after right of way had been acquired, in order to comply with VDOT’s policy titled “Practical Design Flexibility in the Project Development Process,”.  
 

Displaying questions 1 - 8 (of 8)