Subject: New 14-inch forcemain Type: Specifications
Question Date: 9/15/2015 4:21:09 PM
Is the new 14-inch force main PVC or ductile iron pipe? If ductile iron should it be P401 lined?  
Answer   Date: 9/17/2015 10:35:49 AM
This pipe should be 14” CL52 DIP with exterior bituminous coating, a P-401 interior lining with a polyethylene encasement.  
 
Subject: Revision 1 Type: Proposal
Question Date: 9/15/2015 1:59:46 PM
Per Revision 1, the removal of the 107.15 provision; does this mean we no longer have a DBE goal of 12%? If so should the C-111 be re-issued to show this revision?  
Answer   Date: 9/16/2015 4:17:40 PM
There is still a 12% DBE requirement. The revision adds a requirement for the REPORTING of SWaM participation. No SWaM goal.  
 