Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
I04
98372
(NFO)0784-076-051,M501
8/21/2015
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Signal
Type:
Plan
Question
Date:
8/18/2015 1:45:01 PM
The general notes B.2 states the CONTRACTOR shall provide, install and adjust controller timings. In the past VDOT has always supplied the timings. Is this a mistake in the wording of the note?
Answer
Date:
8/19/2015 9:05:01 AM
The initial timing is provided in the plans and the Contractor is responsible for the initial timing adjustments.
Subject:
SIgnal
Type:
Plan
Question
Date:
8/18/2015 1:41:09 PM
The general notes E.7 state the CONTRACTOR is responsible for any costs related to providing power to the traffic signal. These are costs the project has always handled in the past. How is the contractor do determine these costs, pre bid, when typically a service request has to be made and an engineer of the power provider has to design it?
Answer
Date:
8/19/2015 9:17:46 AM
The contractor is responsible to maintain power for the signals for the entire duration of the project. Including in this is Uninterruptible power supply battery, cabinets and signals, which are paid under item, number 52002, 3 EA. This is in addition to continuous power supply during the switch to the new signals.
Subject:
Contract Completion Date/Provisional Completion
Type:
Proposal
Question
Date:
8/12/2015 8:30:02 AM
Completion date in the contract is May 16, 2016. The Provisional Completion date is April 11, 2016. What is true completion date May 16, 2016 or April 11, 2016? If April 11, 2016 is the true completion date. Incentive to complete prior to April 11, 2016 is $2,000.00 per day on or before capped at $60,000.00. Disincentive is $2,000.00 per day each day after April 11, 2016. Will disincentive be capped at $60,000.00 prior to contract completion date of May 16, 2016?
Answer
Date:
8/12/2015 11:30:21 AM
Please see the revised dates which show new dates for both Completion and Provisional Completion dates that were issued in the July 28, 2015 addendum. The new Provisional completion is June 20, 2016 while the new completion date is July 26, 2016. The contractor will be rewarded every day if achieved Provisional completion prior to June 20, 2016 with up to 30 days. If contractor failed to provisionally complete on June 20, 2016 there will be a disincentive of $2000.00/ day until they provisionally complete and there is no cap for disincentive.
Subject:
Concrete Paving
Type:
Plan
Question
Date:
8/11/2015 8:06:09 AM
Plan sheet 6 in the legend shows concrete paving symbol. This concrete paving is located at station 34+00 right of centerline. How is this work to be paid for in the contract?
Answer
Date:
8/13/2015 2:07:06 PM
The existing concrete driveway is being replaced and will be paid under “Hydr. Cement Conc. Sidewalk 7".
Subject:
Storm Drainage Installation
Type:
Plan
Question
Date:
8/11/2015 7:56:07 AM
Plan sheet 3 & 4 show the installation of new storm drainage parallel with the existing curb & gutter station 301+00 to 305+00. In order to install drainage in this area the existing curb & gutter will need to be removed and replaced along with the concrete driveway entrances. Plans do not indicate to remove & replace the existing curb & gutter in this area or driveways. How will the contractor be compensated for this additional work?
Answer
Date:
8/13/2015 3:07:54 PM
It is VDOT belief that the 18” and 21” drainage pipe line are mostly under the sidewalk rather than the C&G, which is why the plan shows the sidewalk to be replaced. If in the field it is determined that there is a need also for the C&G to be removed, it would be covered under LS Grading, item number 00134 and the new C&G placement would be covered under the item number 12600, STD Comb. Curb & Gutter CG-6
Displaying questions 1 - 5 (of 5)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/28/2024 6:38:54 PM
2008