Advertisements   Division Home   Bid Results   Bid Tabs   Ad Report   VDOT Forms
Project Info
Order Number UPC State Project Number Last Date to Post Questions
H89 8312 (NFO) 0709-001-208,C501 6/19/2015
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Demo Type: Other
Question Date: 6/4/2015 11:05:06 AM
There are multiple items listed for demolition that are indicated on Sheet 2F1 to be included in the clearing of the parcel. For example, Biditem 960 is for demo of an 8" waterline on Parcel 008. Biditem 1230 is for Clearing of parcel 008. The chart indicates that the waterline demo should be included in the clearing. It seems that this item is being included in two different biditems. Please clarify.  
Answer   Date: 6/17/2015 3:47:33 PM
The addendum dated 6/12/2015 has addressed these issues.  
 
Subject: Item 24160 - Construction Signs Type: Bid Sheet
Question Date: 5/21/2015 2:30:07 PM
Bid Sheet lists 11,618 sf as the total amount for this project. After reviewing the plans and specifications, it seems this number is elevated by quite a bit. I found an estimated figure around 500 sf. Can this quantity on the bid sheet be verified? Thank you.  
Answer   Date: 5/26/2015 10:47:45 AM
The Department has checked this item and it appears to be estimated at 965sf. An addendum will be issue for this change.  
 

Displaying questions 1 - 2 (of 2)
Page: 1 First Previous Next Last