Subject: USACE Permit Type: Permits
Question Date: 12/11/2014 4:02:53 PM
Reference Special Provision S107J30-0914 VPDES Construction Activities, page 90, Section 107.02: confirm what project scope, if any, is “encumbered” by a U.S Army Corps of Engineers permit?  
Answer   Date: 12/15/2014 3:26:25 PM
An Army Corps of Engineers permit is not required for this project, however a VPDES permit is still needed.  
 
Subject: Approach Slab Type: Bid Sheet
Question Date: 12/11/2014 1:57:25 PM
The concrete quantity for the approach slabs that will be paid per "Plan Quantity" appear to be well short of theactual takeoff quantity. Will these be adjusted per addendum?  
Answer   Date: 12/15/2014 3:29:55 PM
VDOT designers have reviewed and concluded that it is correct.  
 
Question Date: 12/11/2014 1:58:11 PM
The rebar for the approach slab is not identified as CRR in the drawings. Is plain rebar to be used?  
Answer   Date: 12/12/2014 11:55:21 AM
Plain rebar is specified in the approach slabs.  
 
Question Date: 12/11/2014 1:58:03 PM
The rebar for the approach slab is not identified as CRR in the drawings. Is plain rebar to be used?  
Answer   Date: 12/12/2014 11:55:41 AM
SAME  
 
Subject: WMATA Tunnel Type: Other
Question Date: 12/11/2014 1:48:19 PM
As a remnant of the original construction of the WMATA tunnel, did any support of excavation system or parts associated with the S.O.E remain that may impact this project?  
Answer   Date: 12/12/2014 11:47:55 AM
The details of the support of excavation (SOE) for the original construction of the WMATA tunnel were not available and are not known.  
 
Subject: Bid Date Type: Proposal
Question Date: 12/11/2014 12:08:31 PM
With so many unanswered questions, and the bid less than one week away, will VDOT consider postponing the bid until next month?  
Answer   Date: 12/11/2014 2:21:20 PM
Not at this time. We are still answering them.  
 
Subject: Stone Masonary Type: Plan
Question Date: 12/10/2014 10:34:58 AM
1. Please confirm that elevation View B on sheet 26/95 applies to both sides of Abutment B. 2. Please confirm there is no new granite below top 2 courses at elevations A-A and B-B for piers 2,3,4. 3 Please confirm that the stone at piers 2,3,4 is setting on a concrete hunch but at 1 and 5 sets on top of footing. The plan views and section views contradict.  
Answer   Date: 12/16/2014 1:50:19 PM
1. Wingwall Architectural Elevation View B on sheet 26/95 is drawn for the Abutment B west wingwall. The architectural treatment details shown are similar and opposite for the Abutment B east wingwall. 2. As shown on sheet 31/95 and in Views A-A and B-B on sheet 40/95, at the west end of Piers 2,3,4, only the top beveled stone masonry is removed and replaced with 2 courses of new stone masonry. 3. As shown on sheets 38/95 and 40/95 the stone masonry at Piers 2,3 and 4 is set on a concrete hunch to match the existing pier detail. As shown on Section C-C on sheets 30/95 and 45/95 the stone masonry at Piers 1 and 5 is set on the top of footing.  
 
Subject: Bridge Conduit Quantity Type: Plan
Question Date: 12/9/2014 5:07:08 PM
Sheet 66 of 95 Slab Curb shows 4 electrical conduit and references Sheet 77 for details. Section B-B on Sheet 77 shows one conduit required for lighting. Please confirm that only one is required.  
Answer   Date: 12/16/2014 1:47:30 PM
Please bid the conduit according to the LF quantity.  
 
Subject: Drille Shaft Wet Construction Clarification Type: Proposal
Question Date: 12/9/2014 4:18:22 PM
SP for Drilled Shafts Section VII.3. Wet Construction Method and 5. Permanent Casing Construction Method are contradictory and require clarification. Paragraph 3 states “The wet construction method may be used in combination with the dry method and temporary or permanent casing methods.” Paragraph 5 appears to preclude the use of wet construction for permanent casing installation. Please confirm that the installation of the permanent 36 inch casing in a 36 inch slurry filled hole is allowed as stated in Paragraph 3.  
Answer   Date:
 
 
Subject: Masonry Stone Items Type: Proposal
Question Date: 12/8/2014 2:19:10 PM
1. Please confirm that joints at last radial course will be staggered at the pier radial nosing? Sketches can be forwarded if needed for clarification. 2. Can we fabricate tip (pointy) stone with solid nosing? Sketches can be forwarded if needed for clarification. 3. Is pay item for stone masonry net or gross? Stone suppliers charge for the section of stone required to fabricate piece. Furthermore, the price of radial and straight granite facing is quite different. Please advise. 4. Stone at wing walls (abutments) seems to be thicker than 8”. Re-fabrication of stone thickness at new wing wall to accommodate new 11” thickness will be paid under the lump sum or as a separate item. 5. Please confirm that incidental cleaning of stone is to be included in the stone masonry pay item or wing wall lump sum as applicable and is to be limited to high pressure wash, no chemicals or detergents are to be used.  
Answer   Date: 12/15/2014 3:36:23 PM
1. Vertical masonry joints at the pier end nosing shall be staggered similar to detail at existing piers. At existing Piers 2, 3 and 4, vertical masonry joints in the new top courses shall be aligned with joints in the existing lower courses. See attached photo.~~~2. The pier end (pointy tip) shall be fabricated from a solid section of masonry to match existing. Vertical joints shall not be located at the pier end (pointy tip). See attached photo. ~~~3. The pay item for stone masonry shall be based on the dimensions shown on the plans (net). ~~~4. The cost of any tooling of the existing masonry for re-use in the new wing walls shall be included in the Salvaged and Reused Masonry lump sum pay item. ~~~5. Per the specification, the cost of cleaning existing stone masonry shall be included in the Masonry Repointing pay item, the cost of cleaning new masonry and salvaged /reused masonry shall be included in their respective pay items. Cleaning methods and chemicals used shall be per the Special Provision for Stone Masonry.  
 
Subject: Bridge Inspection Report Type: Other
Question Date: 12/4/2014 1:23:27 PM
Can the last bridge inspection report be made available to the bidders?  
Answer   Date: 12/12/2014 3:48:36 PM
It will be posted by Monday on the Construction website under ANNOUNCEMENTS.  
 
Subject: 18 Inch Jacked Pipe Type: Plan
Question Date: 12/4/2014 11:25:20 AM
We are being told that 18 inch pipe cannot be jacked and needs to be installed in a casing. What is the minimum size requirement for the casing?  
Answer   Date: 12/12/2014 3:39:47 PM
Please refer to section 302.03 (a) 1 for further guidance on Jack and Bore installation method.  
 