G28
1491
(NFO)0712-055-P71,C501,B618
11/14/2014
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Rip Rap Limits
Type:
Plan
Question
Date:
10/6/2014 11:08:01 AM
Sheets 1 and 2 of the bridge plans detail the Class III Riprap for the project. From these sheets, we are able to determine the depth and length (east-west distance) of the riprap. It is not clear what the width (north-south distance) is for the riprap. Furthermore, it appears that Sheet 1 is showing the riprap extending 25' beyond the backwall on the slopes at each side of the bridge. No width is given here either. Riprap is being paid as a plan quantity, so we need these dimension to be able to verify the contract quantity. Please clarify the riprap limits for the project.
Answer
Date:
10/15/2014 4:15:04 PM
This will be addressed via addendum. The receipt of bids has been delayed until November 19th.
Subject:
Abutment Preboring
Type:
Proposal
Question
Date:
10/6/2014 10:14:31 AM
The "Estimated Quantities - Substructure Only" table on sheet 2 of the bridge plans shows 94 LF of 'Preboring for 12" Steel Piles Abutment'. The notes on this sheet state that the #8 stone should be included in preboring at the abutment. There is no 'Preboring for 12" Steel Piles Abutment' line item in proposal. How are the abutment preboring and #8 pile backfill stone to be paid?
Answer
Date:
10/15/2014 4:15:15 PM
This will be addressed via addendum. The receipt of bids has been delayed until November 19th.
Subject:
Existing Plans
Type:
Other
Question
Date:
10/2/2014 9:50:52 AM
Please post the plans for the existing bridge.
Answer
Date:
10/3/2014 3:47:36 PM
It is posted on the Construction website under Announcements: http://www.virginiadot.org/business/const/
Displaying questions 1 - 3 (of 3)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/28/2024 2:07:58 AM
2008