Subject: Impact Attenuator Type: Plan
Question Date: 10/17/2014 12:59:13 PM
An impact attenuation unit is called for in the bid sheet, but there is not one on the plan. Please clarify.  
Answer   Date:
 
 
Subject: Piles Type: Specifications
Question Date: 10/17/2014 8:36:16 AM
Sheet 2 of 31 of the bridge plans, “General Notes (Continued)” identify the prebored hole size at 24”. The sheet also shows a bearing plate of 12”x12” as a detail. Section 403.06(d).6 states preboring holes must be between 110% and 120% of the pile area, which would be 1.1 to 1.2 square feet based on the bearing plate area. A 24” diameter hole has an area of 3.14 square feet. Please clarify.  
Answer   Date:
 
 
Subject: Right of way monumenjts Type: Plan
Question Date: 10/16/2014 2:16:33 PM
Sheet 3RW note 6 states "All monumentation to be set upon completion" Who's responsibility is this? The contractor's or VDOT's?  
Answer   Date: 10/17/2014 8:11:35 AM
VDOT will set all RW monuments. It will be the contractors responsibility to reset them if disturbed during construction.  
 
Subject: Railroad Utilities Type: Other
Question Date: 10/6/2014 10:54:35 AM
Are the overhead railroad utility lines going to be relocated prior to the start of this project? If so, where will they be relocated too?  
Answer   Date: 10/9/2014 11:21:35 AM
The railroad utility lines are not in service, so they will not be relocated. These lines will be removed by the railroad. We expect this work to be performed prior to construction.  
 

Displaying questions 1 - 4 (of 4)