Subject: CTA Type: Other
Question Date: 10/16/2014 10:58:13 AM
It has come to my attention that there may be CTA on this project in the same amount as the Select Material Type I Min CBR 30. Please advise.  
Answer   Date:
 
 
Subject: Completion Date Type: Proposal
Question Date: 10/16/2014 7:54:04 AM
The completion date is August 4th, but the time of year restrictions for work in the creek runs from May 15th to July 31st. That only leaves 4 days to complete any remaining work in the stream. Should the completion date be moved further out?  
Answer   Date:
 
 
Subject: Utilities Type: Other
Question Date: 10/9/2014 8:43:05 AM
Will the overhead utilities near the bridge be relocated? If so, to where?  
Answer   Date: 10/15/2014 4:30:38 PM
The railroad utility lines are not in services so they will not be relocated. These lines will be removed by the railroad. We expect this work to be performed prior to construction.  
 
Subject: Superstructure Plans Type: Plan
Question Date: 10/3/2014 9:10:51 AM
There is a note on the plans indicating that plans are available for the existing superstructure. Would you please post those?  
Answer   Date: 10/3/2014 3:04:21 PM
The original plans are not available. The superstructure replacement completed a few years ago to keep the road open until these plans could be finished is what is in the archive folder.  
 

Displaying questions 1 - 4 (of 4)