Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
G36
86599
(NFO)0460-013-774,B635
9/19/2014
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Completion date
Type:
Proposal
Question
Date:
9/11/2014 7:32:08 AM
It seems unlikely that this project will be awarded in time to switch traffic this year pushing the start of construction to spring of 2015. Will VDOT extend to completion date?
Answer
1 previous answer(s)
Date:
9/18/2014 9:56:01 AM
The completion date has been changed to August 10, 2016. It is too late for an official addendum, so a posting under ANNOUNCEMENTS on the Construction website will serve as notice of the change. The final contract will show the completion date as August 10, 2016.
Question
Date:
9/18/2014 8:03:07 AM
The completion date for this project seems unreal. With the amount of work to be done prior to switching traffic, and even afterwards, the completion date, as set, would be almost impossible to meet. Would VDOT consider extending the completion date prior to bid?
Answer
Date:
9/18/2014 9:55:10 AM
The completion date has been changed to August 10, 2016. It is too late for an official addendum, so a posting under ANNOUNCEMENTS on the Construction website will serve as notice of the change. The final contract will show the completion date as August 10, 2016.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/19/2024 10:17:32 PM
2008