Advertisements   Division Home   Bid Results   Bid Tabs   Ad Report   VDOT Forms
Project Info
Order Number UPC State Project Number Last Date to Post Questions
G36 86599 (NFO)0460-013-774,B635 9/19/2014
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Completion date Type: Proposal
Question Date: 9/11/2014 7:32:08 AM
It seems unlikely that this project will be awarded in time to switch traffic this year pushing the start of construction to spring of 2015. Will VDOT extend to completion date?  
Answer   1 previous answer(s) Date: 9/18/2014 9:56:01 AM
The completion date has been changed to August 10, 2016. It is too late for an official addendum, so a posting under ANNOUNCEMENTS on the Construction website will serve as notice of the change. The final contract will show the completion date as August 10, 2016.  
 
Question Date: 9/18/2014 8:03:07 AM
The completion date for this project seems unreal. With the amount of work to be done prior to switching traffic, and even afterwards, the completion date, as set, would be almost impossible to meet. Would VDOT consider extending the completion date prior to bid?  
Answer   Date: 9/18/2014 9:55:10 AM
The completion date has been changed to August 10, 2016. It is too late for an official addendum, so a posting under ANNOUNCEMENTS on the Construction website will serve as notice of the change. The final contract will show the completion date as August 10, 2016.  
 

Displaying questions 1 - 1 (of 1)
Page: 1 First Previous Next Last