Question List
Subject: SIgnalization Type: Plan
Question Date: 8/21/2014 3:29:21 PM
Plan sheet 12(1) Signal Notes B. 3 and 4 referring to the communication line and power to the signal. They state the contractor is responsible for any costs associated with providing these services. Typically the contractor installs the conduit systems but does not have to bear the costs of the utility companies delivering their services and hook-ups. Will this practice continue?  
Answer   Date: 8/22/2014 2:12:31 PM
The contractor is responsible for the dealings with the utility companies and to handle anything else that the utility companies will not handle.  
 
Subject: Construction Sequence Type: Plan
Question Date: 8/11/2014 5:11:55 AM
In construction sequence 5 & 6, is it the intent, to allow traffic to run on aggregate base throughout the sequence at the end of each day until the concrete C&G are installed and the road is paved?  
Answer   Date: 8/13/2014 7:07:19 AM
No, our intent was in those phases to only construct as much as could be replaced each day and not run on the aggregate base.  
 
Subject: Sequence of Construction Type: Other
Question Date: 8/8/2014 12:00:04 PM
In construction sequence 5 & 6, is it the intent, to allow traffic to run on aggregate base throughout the sequence at the end of each day until the concrete C&G are installed and the road is paved?  
Answer   Date: 8/15/2014 12:56:16 PM
No, our intent was in those phases to only construct as much as could be replaced each day and not run on the aggregate base.  
 
Subject: Soil Survey and Pavement Design Recommendations- dated March 22, 2013 Type: Other
Question Date: 7/25/2014 11:22:00 AM
Shallow Rock is discussed on the last page of Mr. David P. Shiells, P.E. letter in which he did encounter diabase rock at shallow depths. Without adequate boring information, estimating the quantity of rock that may be encountered is difficult. Will VDOT be providing more detailed boring information, and if not how will we be paid for excavation should rock encountered?  
Answer   Date: 7/28/2014 12:44:45 PM
VDOT will not be performing any additional borings. All excavation is unclassified so the contractor must make the best estimate on rock excavation he can and take that into account when submitting his bid. The contractor is free to conduct his own investigation prior to submitting his bid. Excavation will be paid in accordance with Section 303 of the Specifications.  
 
Subject: Geotechnical Reports Type: Proposal
Question Date: 7/21/2014 10:48:17 AM
Will the geotechnical reports be issued on CABB for Contractor's review?  
Answer   Date: 7/21/2014 2:33:19 PM
They are now available on Falcon.  
 
Subject: Bid Items & Plans/Proposal Type: Specifications
Question Date: 7/11/2014 9:06:05 AM
When will the bid items be posted on the CABB system? When will the plans and proposal be posted for download on the CABB system?  
Answer   Date: 7/11/2014 11:42:28 AM
They are now posted on CABB.  
 