Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
F61
98134
0005-018-575, B633
8/22/2014
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Temporary Causeway
Type:
Bid Sheet
Question
Date:
7/29/2014 11:01:27 AM
The bid drawings, Sheet 2 of 22, state that the "Temporary Causeway - shall be paid for at the the contract price per lump sum ...", however there is no Bid Item shown for it. Please clarify.
Answer
Date:
7/30/2014 12:42:16 PM
The item will be added by addendum.
Subject:
BR27C Steel Railing
Type:
Plan
Question
Date:
7/28/2014 3:08:28 PM
Please verify the Limits of Payment for the BR27C steel railing as shown on the Bid drawings 18 of 22 and 20 of 22. Drawing 18 shows the railing extending to the face of the backwall and Drawing 20 shows a 7'-3" terminal wall.
Answer
Date:
7/31/2014 7:59:22 AM
Drawing 18 shows two conditions for the terminal wall. The upper left detail shows the terminal wall on the abutment (which does not apply to this job) and the detail on the center left shows the terminal wall on the superstructure (applicable detail). The applicable detail “PART ELEVATION Terminal Wall on Superstructure” on Drawing 18 does not indicate limits of payment and leaves the limits of payment to Drawing 20 which provides additional details for the terminal wall on superstructure. Limit of Payment on Drawing 20 is correct.
Displaying questions 1 - 2 (of 2)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/25/2024 9:20:59 AM
2008