Subject: Completion Date & Project Time Type: Proposal
Question Date: 7/9/2014 12:28:35 PM
August 27 bid date. Contract Execution could be as late as Oct.27, 2014 and a completion date of Jan. 9, 2015. 11 Weeks including Thanksgiving, Christmas, and New Year. Has VDT adequately assessed the time for completion? Will there be a VDOT commitment for early contract execution? Will temperature restrictions for paving and pavement markings be waived?  
Answer   Date: 8/13/2014 5:16:58 AM
An addendum will be issued extending the completion date to May 2015 to allow for paving within temperature guidelines.  
 
Question Date: 8/19/2014 6:45:41 AM
Please supply the 28-day design strength for the A5 concrete in the prestressed voided slabs. Thank you.  
Answer   1 previous answer(s) Date: 8/21/2014 12:42:08 PM
Following note will be added via post-award revision to plans on Sheet 1 of General Notes: Prestressed concrete in all beams shall be Class A5 having a minimum compressive cylinder strength at 28 days equal to 5000 psi and a minimum compressive cylinder strength at time of release of strands equal to 4000 psi.  
 