Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
L14
124646
SG24-965-493, N501
6/21/2024
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
NS Traffic Signalization Guy Wire
Type:
Bid Sheet
Question
Date:
5/30/2024 4:49:30 PM
The pay item for NS Traffic Signalization Guy Wire has a quantity of 6ea. However the measurement and payment states the UOM is to be paid per linear foot. please advise if the UOM should be LF or EA. If the UOM is each, what is to be included in this pay item.
Answer
Date:
6/3/2024 11:20:26 AM
An addendum will be forthcoming to revise the Guy Wire pay item. For clarity, this Guy Wire pay item will be used in cases where the Guy Wire needs to be replaced on an existing wood pole. Line Item 1120 Wood Pole CL. 3, 45', does include the guy wire per Sec. 700.06 of the R&B Spec, "Wood poles will be measured in units of each and will be paid for at the contract unit price per each for the class and length specified. This price shall include furnishing and installing wood poles, thimble-eye bolts, guy wires with guards and anchors, excavating, backfilling, compacting, disposing of surplus and unsuitable material, and restoring disturbed areas." So, in cases, where we use line item 1120 Wood Pole, Guy Wire will not be paid for separately as it is included in the cost of the wood pole.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
11/10/2024 2:45:45 PM
2008