Subject: Crew Requirements Type: Proposal
Question Date: 4/23/2024 9:28:53 AM
Are there any number of crew requirements for simultaneous task orders and/or locations?  
Answer   Date:
 
 
Subject: In Stream Type: Proposal
Question Date: 4/23/2024 9:27:42 AM
Are there any time of year in stream restrictions for fish and wildlife?  
Answer   Date:
 
 
Subject: Permit Restrictions Type: Proposal
Question Date: 4/23/2024 9:26:51 AM
Will the clearing requirements be subjected to the timeline restrictions for the northern long eared bat?  
Answer   Date:
 
 
Subject: GEOTECHNICAL INFORMATION Type: Proposal
Question Date: 4/23/2024 9:25:29 AM
Do any of the proposed locations have geotech reports to enable the bidder to evaluate the load information for site specific engineering and cofferdam design?  
Answer   Date:
 
 
Subject: REHAB DESIGN Type: Specifications
Question Date: 4/17/2024 4:49:45 PM
PIPE REHAB SPEC PROCEDURES CALL FOR THE CONTRACTOR TO SUBMIT WORKING DRAWINGS FOR THE REHAB METHOD SPECIFIED; SIGNED AND SEALED BY A PE LICENSED IN VIRGINIA (REGARDLESS IF PREDETERMINED BY THE OWNER). IS THIS REQUIRED FOR ALL REHAB METHODS? IF NOT PLEASE CLARIFY WHICH REHAB METHODS REQUIRE A PE SUBMITTAL FOR APPROVAL.  
Answer   Date: 4/19/2024 9:33:59 AM
All rehab methods contained within the bid documents are required to be signed and sealed by a professional engineer.  
 
Subject: MOT Type: Specifications
Question Date: 4/17/2024 4:47:57 PM
ONLY RT 615 HANOVER CO IS LISTED ON THE LANE CLOSURE RESTRICTIONS IN THE TEMPORARY TRAFFIC CONTROL SPEC PG 261-262. ARE THERE ANY LANE CLOSURE RESTRICTIONS FOR ANY OF THE 5 OTHER TASK ORDERS IDENTIFIED?  
Answer   Date:
 
 
Subject: CLEARING Type: Bid Sheet
Question Date: 4/17/2024 4:47:07 PM
SELECTIVE CLEARING AND ACCESS ARE REQUIRED FOR SOME OF THE TASK ORDERS PROVIDED. PLEASE CLARIFY HOW CLEARING IS TO BE COMPENSATED IF REQUIRED AND PROVIDE A BID ITEM IF NEEDED.  
Answer   Date:
 
 
Subject: PIPE DETAILS Type: Specifications
Question Date: 4/16/2024 4:29:29 PM
METHOD C REPAIR CALLS FOR SMOOTH WALL STEEL PIPE SLEEVES 0.5" THICKNESS WITH THE ANNULAR SPACE FILLED WITH GROUT. THE SPECIFICATIONS CALL FOR NO MORE THAN 3" OF ANNULAR SPACE ON ANY SIDE OF THE SLEEVE. MANY OF THESE EXISTING PIPES ARE ELLIPTICAL AND SMOOTH WALL STEEL PIPE IS TYPICALLY ROUND/CIRCULAR. PLEASE CLARIFY WHAT TYPE OF PIPE YOU REQUIRE FOR THE SLEEVES AS A ROUND PIPE INSERTED INTO AN ELLIPTICAL PIPE WILL HAVE A MUCH LARGER THAN 3" ANNULAR SPACE TO FILL WITH GROUT.  
Answer   Date: 4/18/2024 7:54:17 AM
Liner shape and size will need to be selected based on the existing pipe. Elliptical liners can be fabricated to maintain compliance with contract requirements.  
 
Question Date: 4/19/2024 1:39:33 PM
PIPE REHAB METHOD C CALLS FOR SMOOTH WALL STEEL PIPE (0.5" THICKNESS) CONFORMING TO 232.02(C)5. STEEL PIPE SHALL CONFORM TO AWWA C200 FOR PRESSURE AND THICKNESS. THE COATING SHALL CONFORM TO AWWA C203 FOR COAL TAR PROTECTIVE COATING, AND THE LINING SHALL CONFORM TO AWWA C205 FOR CEMENT MORTAR LINING. PLEASE CONFIRM IF THIS IS THE PIPE MATERIAL AND SPECIFICATION INTENDED FOR USE WITH ALL THE METHOD C ROUND AND ELLIPTICAL PIPE REHAB ITEMS.  
Answer   Date:
 
 
Question Date: 4/18/2024 9:27:46 AM
PIPE SPECIFICATIONS CALL FOR STEEL WATER PIPE WITH COAL TAR COATING & CEMENT MORTAR LINING WITH BUTT WELDED JOINTS. MANUFACTURES OF THESE APPROVED STEEL WATER PIPE PRIMARILY FABRICATE ROUND PIPES FOR PRESSURE WATER LINES. WILL ALTERNATIVE PIPE MATERIALS BE ALLOWED FOR THESE CULVERT LININGS OTHER THAN STEEL WATER PIPE?  
Answer   Date: 4/19/2024 9:36:02 AM
Contractor's bid should only be based on the rehabilitation methods required under this contract.  
 
Question Date: 4/19/2024 1:39:33 PM
PIPE REHAB METHOD C CALLS FOR SMOOTH WALL STEEL PIPE (0.5" THICKNESS) CONFORMING TO 232.02(C)5. STEEL PIPE SHALL CONFORM TO AWWA C200 FOR PRESSURE AND THICKNESS. THE COATING SHALL CONFORM TO AWWA C203 FOR COAL TAR PROTECTIVE COATING, AND THE LINING SHALL CONFORM TO AWWA C205 FOR CEMENT MORTAR LINING. PLEASE CONFIRM IF THIS IS THE PIPE MATERIAL AND SPECIFICATION INTENDED FOR USE WITH ALL THE METHOD C ROUND AND ELLIPTICAL PIPE REHAB ITEMS.  
Answer   Date:
 
 
Question Date: 4/18/2024 9:27:46 AM
PIPE SPECIFICATIONS CALL FOR STEEL WATER PIPE WITH COAL TAR COATING & CEMENT MORTAR LINING WITH BUTT WELDED JOINTS. MANUFACTURES OF THESE APPROVED STEEL WATER PIPE PRIMARILY FABRICATE ROUND PIPES FOR PRESSURE WATER LINES. WILL ALTERNATIVE PIPE MATERIALS BE ALLOWED FOR THESE CULVERT LININGS OTHER THAN STEEL WATER PIPE?  
Answer   Date: 4/19/2024 9:36:02 AM
Contractor's bid should only be based on the rehabilitation methods required under this contract.  
 
Subject: PIPE DETAILS Type: Other
Question Date: 4/18/2024 9:20:53 AM
TASK ORDER PIPE DIAMETERS PROVIDED ARE NOT SPECIFIC AND ONLY SHOW THE BID ITEM SIZE RANGE. SEVERAL OF THE CULVERTS ARE INACCESSIBLE AND HAVE SIGNIFICANT SILT BUILDUP MAKING IT DIFFICULT TO DETERMINE THE ACTUAL SIZE. CAN THE ACTUAL SIZES AND LENGTHS OF THE PREBID SPECIFIED TASK ORDERS BE PROVIDED?  
Answer   Date: 4/19/2024 9:37:11 AM
No additional information will be provided at this time. Estimated quantities and existing pipe diameter for each location are included in the no plan assembly.  
 
Question Date: 4/16/2024 4:25:12 PM
CAN THE OWNER PROVIDE EXISTING PIPE TYPE AND DIAMETERS FOR THE IDENTIFIED TASK ORDERS AS WELL AS ANY INSPECTION REPORTS?  
Answer   1 previous answer(s) Date: 4/18/2024 10:30:50 AM
No additional information will be provided at this time. Estimated quantities and existing pipe diameter for each location are included in the no plan assembly.  
 
Question Date: 4/18/2024 9:20:53 AM
TASK ORDER PIPE DIAMETERS PROVIDED ARE NOT SPECIFIC AND ONLY SHOW THE BID ITEM SIZE RANGE. SEVERAL OF THE CULVERTS ARE INACCESSIBLE AND HAVE SIGNIFICANT SILT BUILDUP MAKING IT DIFFICULT TO DETERMINE THE ACTUAL SIZE. CAN THE ACTUAL SIZES AND LENGTHS OF THE PREBID SPECIFIED TASK ORDERS BE PROVIDED?  
Answer   Date: 4/19/2024 9:37:11 AM
No additional information will be provided at this time. Estimated quantities and existing pipe diameter for each location are included in the no plan assembly.  
 
Subject: Price Adjustment for Steel Type: Proposal
Question Date: 4/10/2024 12:24:04 PM
Will VDOT provide an Optional Price Adjustment for Steel?  
Answer   Date: 4/11/2024 8:58:11 AM
No, the Department will not provide a steel price adjustment for this project.  
 