Project Info
Order Number UPC State Project Number Last Date to Post Questions
D12 104946 0501-041-762, C501 12/11/2020
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Storm Sewer Type: Plan
Question Date: 12/12/2020 12:06:10 PM
The storm sewer profile plan sheet shows the structures to be cast in place only. Please confirm if this is accurate or if precast structures may be used.  
Answer   Date: 12/15/2020 10:01:16 PM
Those structures will need to be cast-in-place due to their location in relation to the proposed guardrail.  
 
Subject: Hydraulic Cement and Manipulation 8" Type: Bid Sheet
Question Date: 12/10/2020 6:05:52 PM
In the Schedule of Bid Items, Item number 0520 Spec 307 is Hydraulic Cement. Item 0530 Spec 306 is Manipulation 8" Lime Stabilization. Should the Cement be Lime or should the Manipulation be 307 Cement Stabilization?  
Answer   Date: 12/14/2020 6:23:10 PM
Item 0530: Manipulation 8" is for cement stabilization and shall be in accordance with Spec 307 and as shown on Sheet 2A of the Road Plans.  
 
Subject: Work Hour Restrictions Type: Plan
Question Date: 12/9/2020 5:35:36 PM
The Transportation Management Plan states the following: " Work Hour Restrictions: No Construction activities shall be allowed between the hours of 7:00 PM- 6:00 AM." Please confirm that this is accurate and applies to the entire project.  
Answer   Date: 12/14/2020 6:21:56 PM
Yes, these restrictions are accurate and shall apply to the entire project.  
 
Subject: Hydraulic Cement and Manipulation 8" Type: Plan
Question Date: 12/9/2020 3:48:35 PM
How does VDOT anticipate mixing the hydraulic cement into the subgrade and maintaining the flow of traffic on 501?  
Answer   Date: 12/14/2020 6:18:42 PM
The contract documents allow the contractor to maintain one-way traffic on portions of Rte. 501 during certain phases of the project to assist with the cement stabilized subgrade. The contractor shall be responsible for the means and methods of accomplishing the cement stabilized subgrade and maintaining traffic but as an example may shift traffic within the proposed roadway section to accomplish this.  
 
Subject: Cement Stabilization Type: Plan
Question Date: 12/9/2020 3:41:09 PM
Due to the phasing of the project and the use of soil cement stabilization as well as the maintenance of existing traffic. Will MOT stone and traffic be allowed to be immediately placed on top of the cement stabilization? If not what is the time frame it which it would be allowable?  
Answer   Date: 12/14/2020 6:21:01 PM
The contractor shall follow section 307.05 of the Specifications for cement stabilization. Traffic will not be allowed on the areas until the cement stabilized subgrade is protected by means of placement of the subsequent base stone and asphalt base mix course. The subsequent base stone course may be placed immediately after the cement stabilization has been approved.  
 
Subject: Number 10 Screenings Type: Bid Sheet
Question Date: 12/7/2020 3:53:11 PM
Revision #1 includes specification for use of number 10 screenings for stabilizing soft or unsuitable soils. However, it appears the bid item for the number 10 screenings has not been included in the revised bid sheets. Will this be added in another revision?  
Answer   Date: 12/11/2020 1:36:13 PM
The use of number 10 screenings have not been specified for use in the contract or plans. The intent of this special provision is to allow the contractor to submit for approval the use of number 10 screenings in certain applications in lieu of the specified material in the contract and plans. All costs associated with the use of number 10 screenings and meeting the requirements of the special provision shall be included in the costs of appropriate items as there will be no separate payment made for number 10 screenings.  
 
Subject: MOT Type: Plan
Question Date: 12/2/2020 2:33:02 PM
After reviewing the cross-sections, we cannot see how you can maintain one-way traffic and place the embankment. For example, Sta. 172+00 to 180+50 has embankment of 10'-14' over the existing roadway. Please clarify how this is to be constructed.  
Answer   Date: 12/8/2020 10:32:03 PM
The project shall be constructed in accordance with the contract documents, the Traffic Management Plan, and with the 2011 Edition of the Virginia Work Area Protection Manual (VWAPM) Revision 2 (09/01/2019), while maintaining one-way traffic with a shoulder wide enough to place Group 2s and facilitate safe access for construction equipment and traffic with a 6:1 desired, 4:1 minimum safety wedge. The contractor shall be responsible for the means and methods of accomplishing this but as an example may construct the grade by stair stepping the grade shifting the travel lane back and forth as the grade is raised or lowered.  
 
Subject: Excavation Type: Other
Question Date: 12/2/2020 11:53:33 AM
Will over excavating of slopes be allowed as long as it is within the ROW and does not affect drainage?  
Answer   Date: 12/8/2020 10:32:44 PM
The successful bidder may submit a request to over excavate slopes to the Engineer for review and consideration. Environmental and hydraulic impacts would have to be reviewed and considered prior to a determination.  
 
Subject: Double Handling Type: Proposal
Question Date: 12/2/2020 10:12:52 AM
Will double handling of excavated material be paid as Regular Excavation or as Borrow?  
Answer   Date: 12/9/2020 10:38:56 AM
Excavation of material onsite requiring more than one handling prior to final placement will be paid for at the contract unit price for regular excavation for each handling as approved by the Engineer.  No payment for additional handlings will be made if the contractor elects to handle the material more than once for his own convenience.  Borrow excavation shall consist of approved material required for the construction of the roadway and shall be obtained from approved sources outside the project limits and will be measured and paid for as borrow excavation.  
 
Subject: Temporary Guardrail Type: Plan
Question Date: 12/2/2020 10:10:36 AM
While maintaining traffic in one direction of Phase 3 and Phase 4, is the contractor responsible for temporary guardrail as the fill height raises? Is there a minimum shoulder width to maintain?  
Answer   Date: 12/8/2020 10:36:41 PM
The Department does not anticipate the need for temporary guardrail as long as the contractor maintains a minimum shoulder width of 3' to place Group 2s and facilitate safe access for construction equipment and traffic with a 6:1 desired, 4:1 minimum safety wedge. Should the chosen means and methods include the use of temporary guardrail while the fill heights are being raised, the successful bidder can submit a request to the Engineer for review and consideration. All costs associated with temporary guardrail would be included in the costs of other items as there will be no separate payment made for temporary guardrail on this project.below  
 
Question Date: 12/7/2020 11:32:24 AM
Grading in Phase 2A & 2B creates the same issues contemplated in the question regarding Phase 3 & 4. Would the contractor be responsible for temporary guardrail as the fill height rises?  
Answer   Date: 12/11/2020 11:26:52 AM
The Department does not anticipate the need for temporary guardrail as long as the contractor maintains a minimum shoulder width to place Group 2s and facilitate safe access for construction equipment and traffic with a 6:1 desired, 4:1 minimum safety wedge. Should the chosen means and methods include the use of temporary guardrail while the fill heights are being raised, the successful bidder can submit a request to the Engineer for review and consideration. All costs associated with temporary guardrail would be included in the costs of other items as there will be no separate payment made for temporary guardrail on this project.  
 

Displaying questions 1 - 10 (of 21)