Subject: Weight limit Type: Plan
Question Date: 10/15/2020 12:50:17 PM
Will the current repairs being done on The Otter Creek bridge up the weight limits for accessing the site from the West?  
Answer   Date: 10/16/2020 11:33:22 PM
The current repairs on Rte. 40 over Otter Creek are being done under our PM contract, which include Concrete Superstructure Surface Repairs and Concrete Substructure Surface Repairs and should not affect the weight limits of that structure.  
 