Order Number UPC State Project Number Last Date to Post Questions
D08 104187 0622-009-794,M501,B668 8/21/2020
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Railroad Flagging Type: Proposal
Question Date: 8/18/2020 2:00:41 PM
Can a detailed breakdown of the Railroad Force Account Estimate be provided to show the number of days accounted for in the flagging?  
Answer   Date: 8/20/2020 10:23:42 AM
Please see Page 159 of the proposal for this information.  
 
Subject: Pier Demolition Type: Proposal
Question Date: 8/18/2020 1:57:18 PM
On Page 148 of the proposal in the Norfolk Southern Railway Work Requirements SP, it states in the Demolition Procedure that "Existing, obsolete, bridge piers shall be removed entirely to enable restoration of the existing/proposed track ditch." With no plans available of the existing bridge, would it be possible to more clearly define the scope of this activity, so that unexpected conditions can be addressed by change order? Because, what if H-pile is present, or an unusually deep concrete foundation?  
Answer   Date: 8/19/2020 11:52:57 AM
Existing obsolete, bridge piers shall be removed to a sufficient depth below grade to enable restoration of the existing/proposed track ditch, but in no case less than 2’-0” below final grade.“  
 
Subject: Right of Way Monuments Type: Plan
Question Date: 8/17/2020 9:02:37 AM
Under Incidentals in General Notes 1-10 on Plan Sheet 2, Standard RM-1 Right of Way monuments shall be installed by the Contractor. However, in the notes on the Right of Way Plans (Sheets 3RW & 4RW) it list RM-2 monuments. Please clarify.  
Answer   1 previous answer(s) Date: 8/21/2020 10:53:41 AM
Both sheets should specify RM-2 monuments to be installed by state forces.  
 
Subject: Existing Bridge Type: Plan
Question Date: 8/13/2020 11:56:08 AM
Are existing bridge plans available?  
Answer   Date: 8/17/2020 8:34:57 AM
No, existing bridge plan are not available.  
 
Subject: Terminal Walls Type: Plan
Question Date: 8/3/2020 1:07:52 PM
Last note on Sheet 19 of the bridge drawings indicated there is a bid item for the terminal walls. Will there be an item added or which item is this referring too?  
Answer   Date: 8/4/2020 1:33:23 PM
The terminal walls are included in the Railing CPSR 2 Rail superstructure quantity (276 LF).  
 
Subject: Hazardous Material Testing Type: Other
Question Date: 7/30/2020 1:13:59 PM
Has any testing for hazardous material been performed on the structure to be demolished? Such as asbestos, lead, etc? If so can the reports be provided?  
Answer   Date: 7/31/2020 11:45:32 AM
Asbestos Report for this bridge has been posted to ProjectWise. Bidders shall refer to sections 411 and 413 of the spec book for guidance on the Departments requirements for proper removal of material.  
 
Subject: Roadway Plans Type: Plan
Question Date: 7/20/2020 3:33:47 PM
Are Roadway plans available to post to ProjectWise?  
Answer   Date: 7/20/2020 3:43:01 PM
They are available under the plan set.set and under the merged pdf plan set.set.  
 
Question Date: 7/22/2020 11:00:16 AM
Please provide the grading plans for the project. They are not on ProjectWise as described in the answer previously given.  
Answer   Date: 7/23/2020 7:14:14 AM
This is a “M” project, so there is not a particular Grading Plan sheet, however all information including cross sections, profiles, etc. should be able available in ProjectWise.  
 
Question Date: 7/21/2020 10:38:28 AM
Only 37 pages of bridge plans are in "Merged Plan Set" and "Plan Set" on ProjectWise.  
Answer   Date: 7/23/2020 7:13:22 AM
All available plan sheets are now available in ProjectWise.  
 